Data center site feasibility study: power, flood, seismic and zoning screen in 24 hours

A data center site feasibility study from Invariant: power at nearby substations, flood zone, seismic, wetlands, FAA, zoning and parcel checks, with a go or no-go in 24 hours.

A data center site feasibility study tells you whether a site deserves real money before you option it. Send Invariant a coordinate or parcel and a target MW. Within 24 hours you get the serving utility and ISO, the nearest substations and lines with a screening MW range for each of the next three study years, and checks on flood zone, seismic hazard, wetlands and species, airports, zoning, moratoriums, water, fiber and the parcel. It ends in a plain go, no-go or conditional go, with the reason.

Before you start

  • The screen is built to kill sites fast. Power and flood remove more sites than anything else.
  • Every check names its source, so you can show your investment committee where a finding came from.
  • A screening MW range is not a utility commitment. It tells you whether a full power study is worth running.
  • Sites that pass go to step two, the utility-grade power study, with the same team and the same model.

What the screen covers

CheckWhat we look at
PowerServing utility and ISO, nearest substations and lines with voltage and distance, a screening MW range at each for the next three study years, the constraint that sets it
FloodFEMA flood zone on the pad and the access road, base flood elevation where mapped, coastal surge and sea level exposure
Seismic and groundUSGS ground motion, ASCE 7 site values, mapped faults, soils and slope
EnvironmentWetlands, listed species, contamination records nearby, and whether a Phase I ESA is the next step
AirspaceAirports and heliports nearby and whether FAA notice is likely for the buildings, stacks or cranes
Land and localParcel, owner and acreage, zoning, data center moratoriums and county sentiment
UtilitiesWater and wastewater, fiber routes, gas for on-site generation
VerdictGo, no-go or go with conditions, with the kill reason or the one question that decides it

The order matters. We run power first, then flood, then the rest, and stop writing when a site fails a hard check. You still get the full record, but the verdict is on page one.

The power check in the screen

We identify the serving utility and balancing area, then every substation and line within reach of the site at a voltage that can carry the load. As a rough guide, 69 kV serves loads up to about 60 MW, 138 kV up to about 200 MW, 230 kV up to about 400 MW and 345 kV up to about 1,000 MW. A radial station fails any load that needs N-1 service.

For each candidate point we estimate headroom from the line and transformer ratings around it, minus the load already announced or filed nearby, for each of the next three study years. The output is a low, mid and high MW figure and the element that sets it.

Hosting capacity maps rarely help here. Nearly all of them cover distribution feeders and generation, not large loads on the transmission system.U.S. Department of Energy

The physical and land checks

Flood comes from FEMA’s National Flood Hazard Layer: we check the zone under the pad, the access road and the substation route, and flag anything in a 1% annual chance zone.FEMAFEMA

Seismic comes from the USGS National Seismic Hazard Model and the ASCE Hazard Tool, which give the ground motion values a structural engineer will design to. Wetlands come from the National Wetlands Inventory and listed species from IPaC. Airspace comes from the FAA’s notice criteria under Part 77.USGSAmerican Society of Civil EngineersU.S. Fish and Wildlife ServiceU.S. Fish and Wildlife ServiceElectronic Code of Federal Regulations

Then the local layer: zoning, data center moratoriums and recent votes in the county, parcel ownership and size, water and wastewater, fiber routes and gas for on-site generation. Data Center Watch tracks projects blocked or delayed by local opposition; we check the county against it and against local news.Data Center Watch

What you get and how fast

  • A one-page verdict: go, no-go or conditional go, with the reason or the one question that decides it.
  • A power table: candidate connection points, voltage, distance, screening MW range by year and binding constraint.
  • A site table: flood, seismic, wetlands, species, airspace, zoning, moratorium, water, fiber, parcel, each with its source.
  • Maps of the parcel, the substations and lines, and the flood and wetland layers.
  • Editable Word and Excel files with the PDF, so your team or your client can reuse them.

Turnaround is within 24 hours of receiving a coordinate and a MW figure. Many sites at once? Send a list. We screen portfolios for brokers and funds, and we work behind an adviser’s name when asked.

More due diligence guides

Questions that come up.

What is included in a data center site feasibility study?

Invariant’s feasibility screen covers power at the nearest substations and lines (a screening MW range for three study years and the binding constraint), FEMA flood zone, USGS and ASCE seismic values, wetlands, listed species, FAA airspace, zoning and moratoriums, water, fiber, gas and the parcel. It ends in a go, no-go or conditional go.

How much does a data center feasibility study cost?

Invariant charges a fixed fee per site, quoted before we start, with lower rates for portfolios. It costs a small fraction of a utility study deposit, which runs from $10,000 to $100,000 at AEP Ohio and $100,000 for large loads in ERCOT.AEP OhioUtility Dive

How fast can I get a site feasibility screen?

Within 24 hours of sending a coordinate or parcel and a target MW to pranav@invariant-ai.com.

Does a feasibility screen tell me how many MW a site can get?

It gives a screening range at each nearby connection point and names what limits it. A firm number needs a power flow with contingency tests, which is step two, and in the end the utility’s own study.

Can you screen many sites at once?

Yes. Brokers, funds and developers send lists of sites and we return a ranked table with a verdict per site, then run full power studies on the ones they pick.

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. FEMAFlood zones ↗
  2. FEMANational Flood Hazard Layer ↗
  3. USGSNational Seismic Hazard Model ↗
  4. American Society of Civil EngineersASCE Hazard Tool ↗
  5. U.S. Fish and Wildlife ServiceNational Wetlands Inventory: Wetlands Mapper ↗
  6. U.S. Fish and Wildlife ServiceIPaC: Information for Planning and Consultation ↗
  7. Electronic Code of Federal Regulations14 CFR Part 77: Safe, efficient use, and preservation of the navigable airspace ↗
  8. U.S. Department of EnergyU.S. atlas of electric distribution system hosting capacity maps ↗
  9. AEP OhioData center tariff ↗
  10. Utility DiveTexas PUC adopts data center interconnection rules ↗
  11. Data Center WatchData Center Watch Q1 2026 report ↗