FAA height limits near airports: what a data center site needs to check

FAA Part 77 for data center sites: when notice is required for buildings, stacks and cranes near airports, the 200 ft and 100:1 tests, and how to check a site.

A data center near an airport may need to file FAA Form 7460-1 before construction. Under 14 CFR Part 77, notice is required for any structure over 200 feet above ground, and for lower structures that would break an imaginary slope from a nearby public-use airport, for example 100 to 1 for 20,000 feet from a runway longer than 3,200 feet. Cranes count. Generator stacks and cooling equipment can count. The FAA’s Notice Criteria Tool tells you from a coordinate and a height.

Before you start

  • Most data center buildings are well under 200 feet, so the slope tests near airports are what usually apply.
  • Construction cranes often need their own filing.
  • File at least 45 days before construction; a determination of hazard can stop or change the design.
  • Heliports and private airstrips can matter too.

The Part 77 tests

TestApplies to
Over 200 ft above ground levelAny structure anywhere
100:1 slope for 20,000 ftPublic-use airports with a runway over 3,200 ft
50:1 slope for 10,000 ftPublic-use airports with shorter runways
25:1 slope for 5,000 ftPublic-use heliports
Electronic Code of Federal Regulations

If a test is met, notice goes to the FAA on Form 7460-1 at least 45 days before construction starts. The FAA then issues a determination of no hazard, sometimes with marking and lighting conditions.Electronic Code of Federal Regulations

How to check a site

Enter the coordinate, ground elevation and the tallest point (roof, stack, crane) into the FAA’s Notice Criteria Tool. It returns whether notice is required.FAA Obstruction Evaluation / Airport Airspace Analysis

In our feasibility screen we list airports and heliports nearby, run the tool at a typical building and crane height for the campus size, and flag any site where height will shape the design.

More due diligence guides

Questions that come up.

Does a data center need FAA approval?

Only if it meets a Part 77 notice test: over 200 feet above ground, or breaking an airport slope surface. Then it files Form 7460-1 and needs a determination of no hazard.Electronic Code of Federal Regulations

Do construction cranes need FAA notice?

Yes, if the crane meets a Part 77 notice test. Cranes are often taller than the finished building.Electronic Code of Federal Regulations

How far from an airport does Part 77 apply?

Up to 20,000 feet from a runway longer than 3,200 feet at a public-use airport, on a 100 to 1 slope, plus the 200 foot test anywhere.Electronic Code of Federal Regulations

Is airspace part of Invariant’s screen?

Yes, alongside power, flood, seismic, wetlands, zoning and the parcel.

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. FAA Obstruction Evaluation / Airport Airspace AnalysisNotice Criteria Tool ↗
  2. Electronic Code of Federal Regulations14 CFR Part 77: Safe, efficient use, and preservation of the navigable airspace ↗