Power due diligence for data center investors and lenders: what to ask before you underwrite

Data center power due diligence for investors and lenders: which utility documents count, what a power study should show, and the red flags in a powered land deal.

For an investor or lender, power due diligence on a data center site comes down to one question: what document stands behind the MW figure in the model, and what would it take to make it firm? A seller’s will-serve letter is a lead. A utility load study for the marketed load at a named point is the first thing worth underwriting. Between the two, an independent power study tells you whether the number is plausible, which upgrades it assumes, and what date is realistic.

Before you start

  • Underwrite the document, not the headline MW.
  • Ask which element limits the MW and which upgrades the date assumes.
  • Model the minimum bill and term in the service agreement, not just the energy price.
  • Check the county for moratoriums and recent votes before you fund an option.

What to ask the seller

  • Which utility document supports the MW figure: indication, will-serve, load study, construction agreement or service agreement?
  • At which point of interconnection, at what voltage, and from which year?
  • Which upgrades does the date depend on, and who pays for them?
  • Is security posted, and in whose name?
  • What are the minimum bill and the term?
  • Are other large loads filing at the same station?
Lawrence Berkeley National Laboratory and The Brattle Group

Our guide to the five rungs of power evidence explains how much each document is worth.

What an independent power study adds

A seller’s study, if there is one, was run for the seller. An independent study tests every connection option, shows the MW by year with and without upgrades, and names the binding element. Where it agrees with the seller, you underwrite with more confidence. Where it does not, you know which question to ask.

Equity buyers already commission this. Ankura’s 300 MW brownfield case for an institutional investor covered line and substation feasibility, ISO timing, zoning, gas, water and a risk matrix.Ankura

Red flags

  • A MW figure with no named point of interconnection.
  • A date that ignores a planned upgrade or a batch study cycle.
  • Proximity to a line offered as proof of power.
  • A county with a moratorium or a recent failed rezoning.
  • No mention of a minimum bill.
Data Center Watch

More due diligence guides

Questions that come up.

What power documents should a lender require for a data center site?

At minimum a utility load study for the marketed load at a named point, and ideally a signed construction agreement with security or an electric service agreement. A will-serve letter alone does not reserve capacity.

Should an investor commission an independent power study?

Yes, before funding an option or LOI. It shows whether the seller’s MW is plausible, which upgrades it depends on, and what date is realistic. Invariant usually returns one within 48 hours.

What is a minimum bill in a data center service agreement?

The amount owed each month regardless of use, tied to contract demand. Berkeley Lab and Brattle found a median of 80% across new large-load tariffs.Lawrence Berkeley National Laboratory and The Brattle Group

Can Invariant review a seller’s power claims?

Yes. Send the site and the seller’s documents; we screen it in 24 hours and run a full power study if it passes.

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. AnkuraBrownfield to data center: technical due diligence to de-risk 300 MW of capacity ↗
  2. Lawrence Berkeley National Laboratory and The Brattle GroupElectricity rate designs for large loads (August 2026) ↗
  3. Data Center WatchData Center Watch Q1 2026 report ↗