Every approval behind a data centre in India.

A data centre in India answers to a central ministry, a state pollution control board, a discom or transmission utility, a fire service and often an airport authority, each with its own threshold. Start with the approvals that can move the design or the energisation date. Keep the evidence for each one tied to the equipment and the site it covers.

Explore the requirements
Illustrative data centre campus and grid substation in India

The field guides

Start with the next decision.

Detailed explanations, working checklists and links to the authorities behind each requirement.

The compliance map

Follow the whole project.

Data centre development and operation in India, checked against primary sources on 21 November 2026. Thresholds and authorities vary by state, by site and by equipment; confirm each one for the parcel before relying on it. Most of the approvals below are issued by state bodies.

01

Land, allotment and building terms

Is the parcel allotted or converted for data centre use, and on what floor area and coverage terms?

Evidence to assembleAllotment letter from the state industrial development corporation or clear title with non-agricultural conversion, the state policy definition the project falls under, FAR, ground coverage and stamp duty terms. Uttar Pradesh’s 2026 policy, for example, gives FAR 3.0 free plus 1.0 chargeable and ground coverage of up to 60% or the bye-law figure, whichever is higher.

Authority and scopeState industrial development authorities and corporations (for example YEIDA in Uttar Pradesh), the revenue department and the local development authority.

02

Power connection and open access

Which document backs the MW, at what voltage, and by what date?

Evidence to assembleLoad sanction from the discom, connection voltage under the state supply code, bay and line at the transmission substation, dual-grid arrangement, open access or captive approvals and the tariff category the site will be billed under. Maharashtra’s Supply Code, for example, puts loads above 10 MVA (20 MVA in metropolitan areas or on an express feeder) on extra high voltage, and makes the consumer pay the additional cost of a multiple-source supply.

Authority and scopeThe distribution company, the state transmission utility and the state electricity regulatory commission; the central transmission utility where the load connects to the inter-state network.

03

Environmental clearance

Does the built-up area trigger prior environmental clearance?

Evidence to assembleBuilt-up area calculation, project category and the application on PARIVESH. In a Rajya Sabha reply of 6 August 2026, reported by Business Standard, the environment ministry said AI data centres do not, per se, need clearance; they need it as building and construction projects above 20,000 sq m of built-up area under item 8(a), or as township and area development projects under 8(b).

Authority and scopeState Environment Impact Assessment Authority (SEIAA), through the PARIVESH portal.

04

Consent to Establish and Consent to Operate

Which pollution category does the site fall in, and when are CTE and CTO due?

Evidence to assembleGenset inventory by capacity and fuel, built-up area, effluent and emissions details. Under CPCB’s January 2025 classification, projects such as data centres whose pollution potential comes from gensets only may be classified by genset capacity and fuel: 1 MVA or more on liquid fuel is Orange, on gaseous fuel Green; building construction of 20,000 sq m or more of built-up area is Orange.

Authority and scopeState pollution control board, under the Water Act 1974 and the Air Act 1981. State boards must adopt the CPCB classification and may categorise new or left-out sectors themselves.

05

Diesel generators and fuel storage

Do the gensets and the diesel tanks meet emission norms and storage licence thresholds?

Evidence to assembleGenset ratings and type approvals (the revised emission standards of November 2022, G.S.R. 804(E), cover sets up to 800 kW; larger engines fall under the 2002 standards, G.S.R. 489(E), regulated by the state board), stack details, tank volumes and layout. Under the Petroleum Rules 2002, Class B petroleum above 2,500 litres needs a licence: the district authority licenses 2,500 to 25,000 litres, and larger quantities need a PESO licence.

Authority and scopeCPCB and the state board for gensets; the district authority and PESO under the Petroleum Rules 2002 for fuel.

06

Water and groundwater

Where does the cooling water come from, and does drawing groundwater need a NOC?

Evidence to assemblePeak and annual water balance, supplier commitment or treated wastewater source, assessment unit status (safe, semi-critical, critical, over-exploited) and the NOC application. CGWA’s 2020 guidelines bar new industry, other than MSMEs, from groundwater in over-exploited units; whether a data centre counts as industry or infrastructure is a site question to settle with the authority.

Authority and scopeCentral Ground Water Authority, or the state groundwater authority where the state regulates.

07

Building plan and fire NOC

Which code governs the building and fire protection, and who signs off occupancy?

Evidence to assembleBuilding plans, fire and life safety design and the fire NOC. The National Building Code 2016 Part 4 classes electronic data processing centres as occupancy E-3 and requires automatic fire detection and alarm, with clean agent, mist or hypoxic air protection allowed.

Authority and scopeLocal development authority or municipal body, and the state fire service.

08

Airport height clearance

Is the site inside an airport’s height control zone?

Evidence to assembleSite coordinates, top elevation of buildings, stacks and cranes, and the AAI NOC or the colour-coded zoning map figure. A height NOC is needed within 20 km of visual-approach and 56 km of instrument-approach airports; it is valid for eight years.

Authority and scopeAirports Authority of India, through NOCAS, under the 2015 aerodrome safeguarding notification (G.S.R. 751(E)).

09

Electrical safety and energisation

Has the electrical installation been inspected before it is energised?

Evidence to assembleSingle-line diagram, substation and genset installation details, test reports and the Electrical Inspector’s approval or self-certification. Each state notifies the voltage up to which owners may self-certify; installations above it are inspected by the Electrical Inspector.

Authority and scopeState Electrical Inspectorate, under the CEA (Measures relating to Safety and Electric Supply) Regulations 2023.

10

State policy registration and incentives

Does the project qualify for the state data centre policy, and has it registered in time?

Evidence to assemblePolicy definition met (for example a park of 40 MW or more under Uttar Pradesh 2026), eligible investment, renewable share where required, registration through the state single window and the incentive claim schedule. Uttar Pradesh’s 2026 policy, for example, repealed its 2021 policy, so confirm which version applies.

Authority and scopeState IT or industries department and its nodal agency; Ministry of Finance for infrastructure status (5 MW of IT load or more).

11

Data, security and customer obligations

What does the facility owe CERT-In and its regulated customers?

Evidence to assembleCERT-In directions of April 2022: incident reports within 6 hours, 180 days of logs kept in India and five years of subscriber records for data centres. Customer-side rules (RBI payment data, SEBI cloud framework, DPDP Rules 2025) set where their data must sit.

Authority and scopeCERT-In under the IT Act 2000; sector regulators for customer data; MeitY for the DPDP Rules.

Keep the record useful

A requirement needs
an owner and evidence.

For each obligation, record the authority, the design assumption, the responsible person, the evidence and the next decision. Review that record when the site layout, equipment, operating mode or jurisdiction changes.

A dated document is useful. A dated document tied to the equipment and conditions it covers is useful when the project changes.