AI data centres in India: gigawatt campuses, IndiaAI GPUs and power (2026)

AI data centres in India include gigawatt-scale campuses at Visakhapatnam and Jamnagar; IndiaAI Mission compute passed 45,000 GPUs by June 2026. Projects and power.

India’s largest AI data centre projects are gigawatt-scale campuses, led by Google’s AI hub in Visakhapatnam, where ground was broken in April 2026, and the multi-gigawatt data centres Reliance has begun building at Jamnagar. Reliance is also to build a 168 MW AI-ready data centre to be leased by Meta. OpenAI is TCS HyperVault’s first customer with 100 MW and plans to scale to 1 GW, and CoreWeave plans 240 MW at AdaniConneX in Navi Mumbai. The IndiaAI Mission had more than 38,000 GPUs onboarded at Rs 65 per hour by February 2026 and more than 45,000 in its shared compute capacity by June 2026.

Before you start

  • Announced gigawatt-scale AI campuses include Google’s AI hub in Visakhapatnam (about US$15 billion over 2026 to 2030), Reliance at Jamnagar, Digital Connexion in Visakhapatnam, TCS HyperVault and AM Green in Greater Noida (MoU).
  • The IndiaAI Mission GPU pool grew from 18,693 (January 2025) to 34,333 (May 2025), 38,000+ at Rs 65 per hour (February 2026) and 45,000+ (June 2026), according to PIB and to Invest India and Cushman & Wakefield.
  • Anarock puts an Nvidia H100 GPU cluster at 30 to 60 kW per rack against 8 to 10 kW traditionally. Power per GPU, not floor area, sizes the site.
  • SBI’s sector report says MeitY AI cloud tenders have required PUE below 1.35.

AI data centre campuses announced in India

ProjectScaleLocationStatus and date
Google AI hub (with AdaniConneX and Nxtra by Airtel)Gigawatt-scale; about US$15 billion over 2026 to 2030VisakhapatnamGroundbreaking 28 April 2026
Reliance AI data centresMulti-gigawatt; more than 120 MW expected online in H2 2026Jamnagar, GujaratUnder construction (February 2026); 168 MW AI-ready data centre to be leased by Meta (June 2026)
TCS HyperVaultAbove 1 GW targeted; OpenAI starting with 100 MW, plans to scale to 1 GWNot disclosedOpenAI deal February 2026
Digital Connexion1 GW; about US$11 billion by 2030VisakhapatnamMoU November 2025
AM Green1 GWGreater NoidaMoU January 2026; first capacity targeted 2028
CoreWeave at AdaniConneX240 MW (3 x 80 MW buildings)Taloja, Navi MumbaiFirst phase expected mid-2028
Yotta D260 MW, scalable to 250 MW; supercluster of 20,736 NVIDIA Blackwell Ultra GPUs, with added capacity from Navi MumbaiGreater NoidaGo-live expected by August 2026
GoogleAdani GroupTechCrunchTechCrunchCushman & WakefieldTata Consultancy ServicesTechCrunchBusiness TodayCommunications TodayCoreWeaveYotta

Announcements are not capacity. Treat MoUs and approvals as intent until there is a power connection agreement and a construction start. Invest India and Cushman & Wakefield’s AI scenario assumes 15% of a 15 GW early-stage pipeline converts, which still yields about 8 GW by 2030.Invest India and Cushman & Wakefield

IndiaAI Mission GPU count, 2025 to 2026

DateGPUs in the poolPrice noteSource
January 202518,693 (including 12,896 H100)Under Rs 100 per hour after a 40% government subsidyPIB release via Principal Scientific Adviser
May 202534,333 (18,417 existing plus 15,916 added)Seven bidders offered commercialsPIB
February 202638,000+ GPUs and 1,050 TPUsRs 65 per hourPIB
June 202645,000+15 compute service providers empanelled (Lok Sabha figures, August 2026)Invest India and Cushman & Wakefield citing PIB; Communications Today
October 2026C-DAC request for empanelment for up to 10,000 AI compute unitsClusters of 4,000, 1,000 or 512 units; each cluster at least 512 units at a single data centre in IndiaMediaNama
Office of the Principal Scientific Adviser (PIB release)Press Information Bureau (MeitY)Press Information BureauInvest India and Cushman & WakefieldCommunications TodayMediaNama

Yotta committed over 10,000 B300 GPUs to the IndiaAI Mission. The seven bidders named by PIB in May 2025 were Cyfuture India, Ishan Infotech, Locuz Enterprise Solutions, Netmagic IT Services, Sify Digital Services, Vensysco Technologies and Yotta Data Services.YottaPress Information Bureau (MeitY)

Power for AI data centres in India

Power per GPU, not floor area, sizes an AI data centre in India. Anarock puts an Nvidia H100 GPU cluster at 30 to 60 kW per rack against 8 to 10 kW traditionally, and SBI notes that air cooling approaches its limits beyond about 15 kW per rack, leading to early adoption of direct-to-chip and immersion cooling. A 100 MW AI hall therefore needs a high-voltage grid connection with a firm energisation date.AnarockSBI CHAKRA Centre of Excellence

Crisil estimates Visakhapatnam’s data centre capacity could equal about 80% of the city’s current peak demand by FY2030. Reliance says its build-out will be supported by its green energy capacity, including surplus solar power in Gujarat and Andhra Pradesh.Deccan HeraldTechCrunch

More on data centres in India

Questions that come up.

How many AI data centres are being built in India?

AI projects of 240 MW or more announced since 2025 include Google and Digital Connexion in Visakhapatnam, Reliance at Jamnagar and CoreWeave at AdaniConneX in Navi Mumbai. TCS HyperVault aims for capacity above 1 GW, and AM Green signed an MoU with Uttar Pradesh for a 1 GW AI data centre in Greater Noida.GoogleTechCrunchTata Consultancy ServicesBusiness TodayCommunications TodayCoreWeave

How many GPUs does the IndiaAI Mission have?

More than 45,000 GPUs in shared compute capacity by June 2026, according to Invest India and Cushman & Wakefield citing PIB. PIB reported more than 38,000 GPUs at Rs 65 per hour in February 2026.Press Information BureauInvest India and Cushman & Wakefield

How much does IndiaAI Mission GPU compute cost per hour?

Rs 65 per hour in February 2026, according to PIB. In January 2025 the price was under Rs 100 per hour after a 40% government subsidy.Press Information BureauOffice of the Principal Scientific Adviser (PIB release)

Which gigawatt-scale AI data centres are under construction in India?

Google broke ground on its gigawatt-scale AI hub in Visakhapatnam on 28 April 2026, and Reliance says it has begun building multi-gigawatt data centres at Jamnagar.Adani GroupTechCrunch

How much power does an AI data centre need in India?

Far more per rack than a conventional data centre: Anarock puts an Nvidia H100 GPU cluster at 30 to 60 kW per rack against 8 to 10 kW traditionally. A 100 MW AI hall needs a high-voltage grid connection with a firm energisation date.Anarock

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. GoogleOur first AI hub in India, powered by a $15 billion investment ↗
  2. Adani GroupGoogle breaks ground on India AI hub ↗
  3. TechCrunchReliance unveils $110B AI investment plan ↗
  4. TechCrunchMeta signs first AI data center deal in India with Reliance ↗
  5. Cushman & WakefieldIndia Data Centre Market Overview H1 2026 ↗
  6. Tata Consultancy ServicesTCS secures investment from TPG to accelerate AI data center business HyperVault ↗
  7. TechCrunchOpenAI taps Tata for 100 MW AI data center capacity in India, eyes 1 GW ↗
  8. Business TodayReliance, Brookfield, Digital Realty JV to invest $11 billion in Andhra Pradesh for 1 GW data centre ↗
  9. Communications TodayUttar Pradesh signs MoU with AM Green Group for 1 GW AI data centre ↗
  10. CoreWeaveCoreWeave enters India with AdaniConneX ↗
  11. YottaYotta to deploy 20,000+ NVIDIA Blackwell Ultra GPUs ↗
  12. Invest India and Cushman & WakefieldIndia's Data Centre Growth Story (October 2026) ↗
  13. Office of the Principal Scientific Adviser (PIB release)India all set to launch its own AI model; 18,693 GPUs offered (January 2025) ↗
  14. Press Information Bureau (MeitY)India’s common compute capacity crosses 34,000 GPUs ↗
  15. Press Information BureauDemocratising AI in India ↗
  16. Communications TodayIndiaAI Mission faces gap between capacity and deployed GPUs ↗
  17. MediaNamaMeitY seeks AI compute providers for up to 10,000 GPUs under IndiaAI Mission ↗
  18. AnarockData Centre: The Blueprint of the Digital Fortress in India (2026) ↗
  19. SBI CHAKRA Centre of ExcellenceData Centres in India: sector report (April 2026) ↗
  20. Deccan HeraldIndia set for five times surge in its data centre capacity by 2030 (Crisil Ratings) ↗