Data centre policy in India: state data centre policies compared (2026)

State data centre policies in India compared: 11 states had policies in force in September 2026 (Invest India). Subsidy, power tariff and stamp duty by state.

Eleven Indian states had dedicated data centre policies in force as of September 2026, according to Invest India and Cushman & Wakefield; India has no notified national data centre policy. As of 21 November 2026, Uttar Pradesh (2026), Gujarat (2026 to 2029), Maharashtra (IT/ITES Policy 2023 and the Integrated Green Data Centre Parks policy of October 2024), Andhra Pradesh (4.0, 2024 to 2029) and Odisha (2022) have published data centre policies or policy chapters. Tamil Nadu’s 2021 policy covered data centres incorporated up to 31 March 2026 and West Bengal’s 2021 policy was valid for five years from September 2021; we found no successor to either.

Before you start

  • Invest India and Cushman & Wakefield counted 11 states with dedicated data centre policies in force as of September 2026.
  • Eligibility thresholds differ widely: 150 MW of IT load in Gujarat’s 2026 policy, ₹500 crore of eligible fixed assets in Tamil Nadu’s 2021 policy, above 2 MW for data centre units in Uttar Pradesh’s 2026 policy.
  • Green power conditions differ: Gujarat requires 51% renewable power for core operations (law-firm summary); Tamil Nadu’s 2021 policy required at least 30%.
  • Uttar Pradesh’s 2026 policy classifies the data centre industry as an essential service under the Essential Services Maintenance Act (ESMA), and Gujarat’s 2026 policy does the same according to a law-firm summary; West Bengal’s 2021 policy did too, but its five-year term has ended.
  • Mumbai held about 50% of India’s operational data centre capacity in H1 2026, according to Cushman & Wakefield.

State data centre policies in India at a glance (checked 21 November 2026)

StatePolicyYearsStatusHeadline incentives
Uttar PradeshUP Data Centre Policy 2026 (G.O. of 9 July 2026)5 years from notificationNotified 2026; repealed the 2021 policyParks (40 MW and above): interest subsidy of 60% for 7 years, up to ₹50 crore, and dual-grid subsidy. Units (above 2 MW, below 40 MW): capital subsidy of 7% up to ₹20 crore and 100% electricity duty exemption for 10 years
MaharashtraIT/ITES Policy 2023 (GR of 27 June 2023); Policy for Integrated Green Data Centre Parks (GR of 9 October 2024)IT policy: five years from 27 June 2023 or until replacedIn force100% stamp duty exemption; ₹1 per unit tariff subsidy for 5 years outside Zone I; electricity duty exemption for 20 years for registered data centre units (notification of 22 June 2026)
GujaratViksit Gujarat Data Centre Policy 2026-293 years from notification; incentives end when 7.5 GW is installedLaunched 9 July 2026Minimum 150 MW IT load; ₹1 per unit for 20 years; electricity duty reimbursed 100% for 20 years; interest subsidy up to 4% for 10 years (law-firm summary)
Tamil NaduData Centre Policy 2021Data centres incorporated 1 April 2021 to 31 March 2026Window closed; we found no successorMinimum ₹500 crore eligible fixed assets and 30% renewable power; electricity tax subsidy 100% for 5 years; open access charges at 50% of conventional
Andhra PradeshData Center Policy (4.0) 2024-29, G.O.Ms.No.6 of 14 November 2024Five years (2024 to 2029)Notified 14 November 2024Target of 200 MW additional capacity; tailor-made incentives for projects above 50 MW or above ₹5,000 crore fixed capital investment in plant and equipment
OdishaState Data Centre Policy 2022Validity not stated in the policyPublished on Invest OdishaCapital subsidy 20% of fixed capital investment up to ₹25 crore per unit; power bill subsidy 30% for 5 years up to ₹2 crore; net SGST reimbursed 100% for 7 years
West BengalData Centre Policy 2021 (notification of 6 September 2021)5 years from notification or until replacedFive-year term ended in September 2026; we found no successor100% stamp duty and registration fee exemption; electricity duty waiver for 5 years; essential services classification; dual power grid networks
Government of Uttar PradeshCyril Amarchand MangaldasGovernment of Maharashtra, Industries, Energy, Labour and Mining Department (gazette copy via Simpliance)Cyril Amarchand Mangaldastele.netDD IndiaGovernment of Tamil Nadu, IT Department, via National Single Window SystemTeamLease RegTechInvest Odisha, Government of OdishaDepartment of IT and Electronics, West Bengal (text via wbxpress)

Invest India and Cushman & Wakefield counted eleven states with dedicated data centre policies in force as of September 2026, with two new policies notified during the preceding year.Invest India and Cushman & Wakefield

Eligibility thresholds and green power conditions by state

StateWho qualifiesGreen power condition
GujaratApproved installed IT load of at least 150 MWAt least 51% of electricity for core operations from green and renewable sources (law-firm summary)
Tamil Nadu (2021)Minimum eligible fixed assets of ₹500 crore; captive data centres excludedAt least 30% of energy consumption from renewable sources
Uttar PradeshParks of at least 40 MW; units above 2 MW and below 40 MW; edge proposals of at least 10 sites of 50 kW or more totalling 2 MW; captive units excludedNo minimum; the policy aims to encourage at least 50% renewable share in new data centres by 2030
Cyril Amarchand MangaldasGovernment of Tamil Nadu, IT Department, via National Single Window SystemGovernment of Uttar Pradesh

Power terms: tariff subsidy, electricity duty, dual grid and open access

StateTariff supportElectricity dutyGrid, open access and siting
Maharashtra₹1 per unit for 5 years for new data centre units outside Zone I20 years for new and existing registered data centre units (notification of 22 June 2026)Data centres may be set up in any zone, including residential and green zones
Gujarat₹1 per unit for 20 years100% reimbursement for 20 yearsOpen access allowed; dual supply through two independent feeders
Uttar PradeshDual-grid subsidy for parks: the state reimburses the cost of one grid100% exemption for 10 years for data centre unitsWheeling and transmission charges exempted for 25 years: 50% on intrastate purchase, 75% for in-state renewable power, 100% of intrastate charges on interstate purchase
Tamil Nadu (2021)Cross subsidy charge at 60% of conventional for wind and 70% for solar, for third-party open accessElectricity tax subsidy 100% for 5 yearsOpen access charges at 50% of conventional; dual grid at 50 MW or more; additional feeder above 100 MW
OdishaPower bill subsidy 30% for 5 years, up to ₹2 crore100% exemption for 10 years up to 5 MVA contract demandTransmission and wheeling charges reimbursed 100% for captive renewable power in the state
West Bengal (2021)Data centre electricity treated as industrialWaiver for 5 yearsDual power grid networks
Cyril Amarchand MangaldasGovernment of Maharashtra, Industries, Energy, Labour and Mining Department (gazette copy via Simpliance)Cyril Amarchand MangaldasGovernment of Uttar PradeshGovernment of Tamil Nadu, IT Department, via National Single Window SystemInvest Odisha, Government of OdishaDepartment of IT and Electronics, West Bengal (text via wbxpress)

States that classify data centres as an essential service

Uttar Pradesh’s 2026 policy says the data centre industry in the state has been classified under ESMA as an essential service provider. Gujarat’s 2026 policy treats data centre operation, management, maintenance and support as an essential service under the Gujarat Essential Services Maintenance Act, 1972, according to Cyril Amarchand Mangaldas; we have not seen the notified resolution. West Bengal’s 2021 policy says data centre organisations "shall be classified under ‘Essential Services’", though that policy’s five-year term has ended.Government of Uttar PradeshCyril Amarchand MangaldasDepartment of IT and Electronics, West Bengal (text via wbxpress)

NITI Aayog’s October 2026 framework proposes bringing data centres under the Essential Services Maintenance Act. The framework is not binding.ThePrint

Lapsed, replaced and unclear state data centre policies

  • Tamil Nadu: the 2021 policy applies to data centres incorporated from 1 April 2021 until 31 March 2026. We found no successor as of 21 November 2026.
  • West Bengal: the 2021 policy was valid for five years from 6 September 2021 or until replaced. In May 2026 the state BJP president said the government was working on a new data centre policy.
  • Uttar Pradesh: the 2026 policy repealed the 2021 policy (First Amendment 2022). Holders of a Letter of Comfort under the old policy that have availed incentives remain eligible for the admissible benefits.
  • Telangana: the state has announced a target of five gigawatts of hyperscale capacity by 2029 (Deccan Chronicle). For Amazon’s Hyderabad project it allocated 202 acres in Bharat Future City and 98 acres in Chandanvelly, with incentives worth ₹125 crore (ThePrint).
  • Karnataka: MediaNama reported in September 2026 that the cabinet approved a Sustainable Data Centre Policy 2026-31 with a budget framework of ₹1,300.45 crore. We had not seen the notified text.
Government of Tamil Nadu, IT Department, via National Single Window SystemDepartment of IT and Electronics, West Bengal (text via wbxpress)Business StandardGovernment of Uttar PradeshDeccan ChronicleThePrintMediaNama

The best state for a data centre depends on size and location

The best Indian state for a data centre depends on the project’s size and location more than on headline incentives. Gujarat’s policy only admits projects of 150 MW or more. Uttar Pradesh has a band for units above 2 MW. Mumbai had 890 MW of operational capacity in H1 2026, about 50% of the national total (Cushman & Wakefield), but Structure Research reports that MSEDCL has allocated about 6 GW of grid power to data centres in Navi Mumbai and that committed and under-construction capacity is approaching that level.Cyril Amarchand MangaldasGovernment of Uttar PradeshCushman & WakefieldStructure Research

Check three things before choosing on incentives: whether the policy is in force on the date your project is registered, whether your load and investment clear its threshold, and whether the power path to the site can deliver the MW on your date.

For a site in any Indian state, Invariant checks how it gets power and the evidence behind that path (the distribution or transmission connection, the open access route, the nearest substations), screens seismic zone, flood history, groundwater status and airport height limits, and maps the central and state approvals the project needs, with the authority behind each one.

More on data centres in India

Questions that come up.

Which states in India have a data centre policy in 2026?

Uttar Pradesh, Gujarat, Maharashtra (through its IT policy and green parks policy), Andhra Pradesh and Odisha have published policies, as of 21 November 2026. Tamil Nadu’s and West Bengal’s 2021 policies have ended without a successor that we found. Invest India counted eleven states with dedicated policies in force as of September 2026.Government of Uttar PradeshCyril Amarchand MangaldasCyril Amarchand MangaldasTeamLease RegTechInvest Odisha, Government of OdishaGovernment of Tamil Nadu, IT Department, via National Single Window SystemDepartment of IT and Electronics, West Bengal (text via wbxpress)Invest India and Cushman & Wakefield

Which state has the most data centres in India?

Maharashtra, measured by capacity: Mumbai had 890 MW of operational capacity in H1 2026, about 50% of India’s total, according to Cushman & Wakefield.Cushman & Wakefield

Does Tamil Nadu still have a data centre policy?

Tamil Nadu’s 2021 data centre policy covered data centres incorporated up to 31 March 2026, and we found no successor as of 21 November 2026.Government of Tamil Nadu, IT Department, via National Single Window System

Which state data centre policies give a power tariff subsidy?

Maharashtra, Gujarat and Odisha are among them. Maharashtra gives ₹1 per unit for 5 years outside Zone I, Gujarat ₹1 per unit for 20 years (according to a law-firm summary) and Odisha a 30% power bill subsidy for 5 years.Cyril Amarchand MangaldasCyril Amarchand MangaldasInvest Odisha, Government of Odisha

Can a data centre combine central and state incentives?

It depends on the state policy. Gujarat’s 2026 policy, for example, bars claiming incentives under other Gujarat policies but allows applicable central policies, according to Cyril Amarchand Mangaldas.Cyril Amarchand Mangaldas

How many Indian states have dedicated data centre policies?

Eleven as of September 2026, according to Invest India and Cushman & Wakefield.Invest India and Cushman & Wakefield

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. Government of Uttar PradeshUttar Pradesh Data Center Policy 2026, G.O. No. 536/78-2-2026/E-105226 dated 9 July 2026 ↗
  2. Cyril Amarchand MangaldasKey highlights of Maharashtra IT/ITES Policy 2023: data centers ↗
  3. Government of Maharashtra, Industries, Energy, Labour and Mining Department (gazette copy via Simpliance)Notification No. CEI-2025/CR-158/Energy-1 of 22 June 2026 under the Maharashtra Electricity Duty Act, 2016 ↗
  4. Cyril Amarchand MangaldasGujarat Data Center Policy 2026-2029: a push for large-scale data center infrastructure ↗
  5. tele.netGujarat government launches Data Centre Policy 2026-29 ↗
  6. DD IndiaGujarat launches Data Centre Policy 2026-29 ↗
  7. Government of Tamil Nadu, IT Department, via National Single Window SystemTamil Nadu Data Centre Policy 2021 (G.O. and policy text) ↗
  8. TeamLease RegTechAndhra Pradesh Data Center Policy 4.0 (2024-29) ↗
  9. Invest Odisha, Government of OdishaOdisha State Data Centre Policy 2022 ↗
  10. Department of IT and Electronics, West Bengal (text via wbxpress)West Bengal Data Centre Policy 2021, notification 490-Estt/ITE-18011/2/2021 of 6 September 2021 ↗
  11. Business StandardBengal government working on land and data centre policies ↗
  12. Deccan ChronicleTelangana targets 5 GW data centre capacity by 2029 ↗
  13. ThePrintTelangana secures Amazon's biggest India data centre project ↗
  14. MediaNamaKarnataka Sustainable Data Centre Policy ↗
  15. Invest India and Cushman & WakefieldIndia's data centre growth story (October 2026) ↗
  16. ThePrintNITI Aayog asks states to verify power and water capacity before clearing data centre projects ↗
  17. Cushman & WakefieldIndia data centre market overview, H1 2026 ↗
  18. Structure ResearchMumbai and Pune data centre report 2026 ↗