Building a data centre in India costs ₹35 crore to ₹75 crore per MW of IT load according to SBI’s April 2026 sector report, which gives ₹35 to 45 crore for large facilities, ₹50 to 55 crore for an air-cooled Tier III build and up to ₹75 crore for AI with immersion cooling or Tier IV. Cushman & Wakefield benchmarks US$7.4 million per MW, about 23% below Malaysia and 26% below Australia, and assumes US$9.0 million per MW for incremental AI capacity in its projections. Anarock prices land separately, at ₹3 crore to ₹60 crore per acre across its size bands, and reports long-tenor debt at about 9.5 to 10.5%.
Before you start
- Cushman & Wakefield: US$7.4 million per MW, about 23% below Malaysia and 26% below Australia; it assumes US$9.0 million per MW for incremental AI capacity.
- SBI (April 2026): ₹50 to 55 crore per MW for air-cooled Tier III, up to ₹75 crore for AI with immersion cooling or Tier IV, ₹35 to 45 crore for large facilities.
- Anarock: ₹40 to 45 crore per MW (low) to ₹65 to 70 crore per MW (high) for a greenfield Tier III N+1 build.
- In Mumbai, wholesale colocation of 5 MW and above rented at about ₹6,000 to 7,500 per kW per month in H1 2025, according to Cushman & Wakefield.
Data centre construction cost per MW in India: published benchmarks
| Publisher | Benchmark | Scope stated |
|---|---|---|
| Cushman & Wakefield, in Invest India’s October 2026 report | US$7.4 million per MW; US$9.0 million per MW assumed for incremental AI capacity | Construction cost benchmark; AI figure is a projection assumption |
| SBI (April 2026) | ₹50 to 55 crore per MW | Standard Tier III, non-AI, air-cooled |
| SBI (April 2026) | Up to ₹75 crore per MW | AI workloads with immersion cooling, or Tier IV |
| SBI (April 2026) | ₹35 to 45 crore per MW | Larger data centres |
| Anarock (2026) | ₹40 to 45 crore per MW to ₹65 to 70 crore per MW (US$4.8 to 8.4 million) | Total greenfield Tier III N+1 |
Anarock prices land separately, per acre. Crisil puts Indian development costs about one fifth below several competing Asia Pacific markets.AnarockDeccan Herald
A cross-check from the sector level: ICRA expected third-party capacity to grow from 1,250 MW in FY2025 to 2,400 to 2,500 MW by FY2028 with an investment pipeline of ₹90,000 crore, which works out (our calculation) to roughly ₹72 to 78 crore per MW added.ICRA
What drives data centre cost per MW in India
- Cooling and density: Anarock maps precision air conditioning (CRAC/CRAH, the most common in India) to 3 to 10 kW per rack, in-row cooling to 15 to 25 kW, rear-door heat exchangers to 20 to 40 kW and direct liquid cooling to 40 to 100 kW or more; it puts an Nvidia H100 GPU cluster at 30 to 60 kW per rack.
- Tier and cooling: SBI puts an air-cooled Tier III build at ₹50 to 55 crore per MW and AI with immersion cooling or Tier IV at up to ₹75 crore.
- Efficiency targets: SBI reports leading Indian operators at PUE 1.4 to 1.5 and MeitY AI cloud tenders since 2024 requiring below 1.35, which pushes design toward more efficient cooling.
- Power infrastructure: Anarock puts DG, UPS, HT supply and switchgear at ₹14 to 22 crore per MW, its largest single line. Ask the discom or transmission utility who pays for the dedicated line, bay and substation.
Data centre land cost in India
| Facility size | Typical land | Land price per acre |
|---|---|---|
| 5 to 10 MW | 2 to 5 acres | ₹35 to 60 crore (Mumbai suburbs); ₹4 to 10 crore (secondary cities) |
| 10 to 30 MW | 5 to 15 acres | ₹5 to 20 crore |
| 30 to 100 MW | 15 to 50 acres | ₹4 to 12 crore |
| 100 to 500 MW | 50 to 200 acres | ₹3 to 10 crore |
Recent transactions sit inside these bands: Zee Business reported in June 2026 that Amazon Data Services bought 10.6 acres from Lodha for ₹125.13 crore, about ₹11.8 crore per acre (our calculation).Zee Business
Colocation rents in India by city
Cushman & Wakefield’s H1 2025 report publishes rents in ₹ per kW per month, assuming standard 5 to 7 kVA racks; its H1 2026 report does not include a rent table.Cushman & WakefieldCushman & Wakefield
| City | Under 250 kW | 250 kW to 1 MW | 1 to 5 MW | 5 MW and above |
|---|---|---|---|---|
| Mumbai | 8,000 to 12,000 | 7,000 to 10,000 | 6,500 to 8,000 | 6,000 to 7,500 |
| Chennai | 8,000 to 9,000 | 7,500 to 8,500 | 7,000 to 8,000 | 6,000 to 7,000 |
| Hyderabad | 7,500 to 9,500 | 7,000 to 8,500 | 6,500 to 7,500 | 6,000 to 7,000 |
| Delhi NCR | 7,500 to 9,500 | 7,000 to 8,500 | 6,500 to 7,500 | 6,000 to 7,000 |
| Bengaluru | 7,500 to 9,000 | 7,000 to 8,500 | 7,000 to 8,000 | 6,500 to 7,000 |
| Pune | 7,000 to 8,500 | 6,500 to 8,000 | 6,000 to 7,000 | 6,000 to 6,500 |
Crisil says Indian rents are 30 to 35% below peer markets and that contract tenors have lengthened to 15 to 20 years from 10 to 12 years.Deccan Herald
Financing and state incentives
Data centres in India with at least 5 MW of IT load have had infrastructure status since 11 October 2022, which eases access to long-term credit; Anarock reports debt at about 9.5 to 10.5% for up to 12 years. State policies cut the effective cost further through capital subsidy, stamp duty exemption and electricity duty exemption: Uttar Pradesh’s 2026 policy, for example, exempts 100% of stamp duty on land bought or leased from a government authority and gives a 25% land subsidy on sector rates in the Paschimanchal region, which includes Gautam Buddha Nagar (Noida).Ministry of Finance, Department of Economic AffairsAnarockGovernment of Uttar Pradesh
How Invariant helps
Cost estimates move most with the power connection and the site. Invariant checks how a site gets power and what the connection depends on, screens seismic, flood, groundwater and airport height risk, and maps the approvals, so the capex model starts from the actual site. Send the state, the MW and the date you need power.
More on data centres in India
Questions that come up.
How much does it cost to build a data center in India per MW?
Building a data centre in India costs about US$7.4 million per MW on Cushman & Wakefield’s benchmark. SBI’s April 2026 sector report puts air-cooled Tier III at ₹50 to 55 crore per MW and AI with immersion cooling or Tier IV at up to ₹75 crore. Anarock prices land separately.Invest India and Cushman & WakefieldSBI CHAKRAAnarock
What is the cost of setting up a data centre in India?
SBI’s figures run from ₹35 to 45 crore per MW for large facilities to up to ₹75 crore for AI or Tier IV, and Anarock’s greenfield Tier III N+1 total runs from ₹40 to 45 crore to ₹65 to 70 crore per MW. Anarock prices land separately at ₹3 to 60 crore per acre across its size bands.AnarockSBI CHAKRA
How much does it cost to build a small data centre in India?
The published benchmarks are per MW and assume purpose-built facilities. Anarock’s smallest land band is 5 to 10 MW on 2 to 5 acres; at Tier III build costs of ₹50 to 55 crore per MW, even a 5 MW facility is a ₹250 crore plus project before land (our calculation).AnarockSBI CHAKRA
Is it cheaper to build a data centre in India than in Malaysia?
Cushman & Wakefield’s 2026 benchmark of US$7.4 million per MW is about 23% below Malaysia and 26% below Australia for a comparable specification.Invest India and Cushman & Wakefield
What is the colocation price per kW in India?
In H1 2025 Cushman & Wakefield quoted Mumbai colocation at ₹6,000 to 7,500 per kW per month for 5 MW and above, and ₹8,000 to 12,000 for deals under 250 kW.Cushman & Wakefield
Sources and references.
Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.
- Invest India and Cushman & WakefieldIndia's Data Centre Growth Story (October 2026) ↗
- SBI CHAKRAData Centres in India, sector report (April 2026) ↗
- AnarockData Centre: The Blueprint of the Digital Fortress in India (2026) ↗
- Deccan HeraldIndia set for five times surge in its data centre capacity by 2030 (Crisil Ratings, 3 November 2026) ↗
- ICRAThird-party data centre capacity to double by FY2028 ↗
- Zee BusinessAmazon Data Services India acquires land from Lodha Developers ↗
- Cushman & WakefieldIndia Data Centre Market Overview H1 2025 (rent tables) ↗
- Cushman & WakefieldIndia Data Centre Market Overview H1 2026 ↗
- Ministry of Finance, Department of Economic AffairsHarmonised Master List of Infrastructure Sub-sectors, notification of 11 October 2022 ↗
- Government of Uttar PradeshUttar Pradesh Data Center Policy 2026 (G.O. dated 9 July 2026) ↗