Emission limits notified by G.S.R. 804(E) of 3 November 2022, which CAQM calls CPCB IV, apply to new genset engines up to 800 kW at Indian data centres from 1 July 2023; diesel engines above 800 kW fall under standards notified in 2002. The pollution board’s consent category and petroleum storage licensing also apply. Under CPCB’s January 2025 classification, a data centre whose only pollution source is gensets is Orange if it has 1 MVA or more on liquid fuel and Green if on gaseous fuel. If the diesel stored is Class B petroleum (confirm the class with PESO), storage above 2,500 litres needs a licence and above 25,000 litres a PESO licence.
Before you start
- G.S.R. 804(E) (CPCB IV) sets emission limits for new genset engines up to 800 kW from 1 July 2023.
- Diesel engines above 800 kW are covered by concentration-based standards notified in 2002 and regulated by state pollution control boards.
- Under CPCB’s January 2025 classification, genset capacity and fuel decide the pollution category of a data centre whose only pollution source is gensets: 1 MVA or more on liquid fuel is Orange; on gaseous fuel, Green.
- Under the Petroleum Rules 2002, for Class B petroleum (confirm the class with PESO): no licence below 2,500 litres, district licence to 25,000 litres, PESO licence above.
- In Delhi NCR, CAQM’s schedule places no restriction, even under GRAP, on gensets up to 800 kW that meet G.S.R. 804(E), as summarised by the Delhi Pollution Control Committee in June 2025.
Emission norms for data centre generators: CPCB IV and above 800 kW
Emission limits for new genset engines up to 800 kW were notified by G.S.R. 804(E) of 3 November 2022 and apply from 1 July 2023, as reported by SCC Online; CAQM refers to these standards as CPCB IV. For engines up to 800 kW, compliance is certified at manufacture: CPCB’s system and procedure provides for a type approval certificate and conformity of production certificates for each engine family.SCC OnlineCommission for Air Quality ManagementCentral Pollution Control Board
| Engine size | Standard | How compliance is shown |
|---|---|---|
| Up to 800 kW | G.S.R. 804(E) (CPCB IV), from 1 July 2023 | Type approval and conformity of production at manufacture |
| Above 800 kW | Standards notified in 2002 (G.S.R. 489(E)); for sets commissioned from 1 July 2005: CO 150 mg/Nm3, NMHC 100 mg/Nm3, PM 75 mg/Nm3 on diesel, NOx 710 ppm(v), or 360 ppm(v) in larger plants | Regulated by the state pollution control board |
| Noise, diesel sets up to 1,000 kVA made from 1 January 2005 | 75 dB(A) at 1 m from the enclosure surface | Integral acoustic enclosure fitted at manufacture |
The NOx limit for sets above 800 kW depends on the total engine rating of the plant and the area category; check the CPCB standard for the version that applies to a given site.Central Pollution Control Board
Pollution category and consent for a data centre
CPCB’s January 2025 classification says projects such as data centres whose pollution potential comes only from gensets may be classified by genset capacity and fuel. Gensets totalling under 1,000 kVA may not need additional classification. Gensets totalling 1 MVA or more on liquid fuel are Orange (pollution index 60.0); on gaseous fuel, Green (50.5). Separately, a building construction project of 20,000 sq m or more of built-up area is Orange.Central Pollution Control Board
CPCB says the classification may be used for consent management and inspection frequency, and generator buildings appear in environmental clearances for large campuses: one 2025 Maharashtra clearance covered two data centre buildings, two DG buildings and a substation. Gas gensets are therefore a consent question as well as a fuel question.Central Pollution Control BoardSEIAA Maharashtra
Diesel storage licences under the Petroleum Rules 2002
| Class B petroleum stored | Licence |
|---|---|
| Below 2,500 litres | No licence needed |
| 2,500 to 25,000 litres | Licence from the district authority |
| Above 25,000 litres | PESO licence, applied for through the National Single Window System and the PESO portal |
PESO lists diesel (HSD) among products that need a licence under the Petroleum Rules 2002. Class B covers flash points from 23°C to below 65°C; confirm the class of the fuel specified for the site with PESO before relying on these thresholds.PESO
Delhi NCR and the Graded Response Action Plan
In Delhi NCR, the Commission for Air Quality Management regulates the use of DG sets, particularly during restrictions under the Graded Response Action Plan. Its schedule, as summarised by the Delhi Pollution Control Committee in June 2025, places no restriction, even under GRAP, on gensets of up to 800 kW that meet the G.S.R. 804(E) standards. For larger sets, check the current CAQM directions and stack standards for the site before relying on generator run hours in a Noida or Gurugram design.Commission for Air Quality ManagementDelhi Pollution Control Committee, via National Green Tribunal
State data centre policy terms for backup power
- Uttar Pradesh 2026: service FAR extended to 40% for DG sets, DG space outside FAR, and multi-level DG stacking allowed with a fire NOC.
- Telangana and Odisha policies list a fuel subsidy for backup power, and Telangana exempts data centres from statutory power cuts, per Cushman & Wakefield’s policy comparison.
- Andhra Pradesh: generating units above 10 kW need Electrical Inspector inspection before commissioning under its March 2026 order.
How Invariant helps
For a site or shortlist in India, Invariant checks how the site gets power: the discom or transmission connection, the voltage the load falls under, the nearest substations, the open access or captive route and the document behind the MW. We also screen seismic zone, flood history, groundwater status and airport height limits, and map the central and state approvals with the authority behind each. Send the state, the MW and the date you need power.
More on data centres in India
Questions that come up.
What emission norms apply to data centre generators in India?
Emission limits under G.S.R. 804(E), known as CPCB IV, apply to new genset engines up to 800 kW from 1 July 2023. Diesel engines above 800 kW fall under standards notified in 2002, regulated by the state pollution control board.SCC OnlineCommission for Air Quality ManagementCentral Pollution Control Board
What pollution category is a data centre in India?
A data centre whose only pollution source is gensets may be categorised by genset capacity and fuel: Orange with 1 MVA or more on liquid fuel, Green with 1 MVA or more on gaseous fuel. That is under CPCB’s January 2025 classification; a building construction project of 20,000 sq m or more of built-up area is separately Orange.Central Pollution Control Board
Does a data centre need a PESO licence for diesel storage?
Above 25,000 litres of Class B petroleum, yes; 2,500 to 25,000 litres needs a district licence instead, and below 2,500 litres no licence. Confirm the fuel class with PESO.PESOPESO
Can data centres run diesel generators in Delhi NCR during GRAP?
CAQM’s schedule, as summarised by the Delhi Pollution Control Committee, places no restriction, even under GRAP, on gensets up to 800 kW that meet the G.S.R. 804(E) standards. For larger sets, check the current CAQM directions for the site.Delhi Pollution Control Committee, via National Green Tribunal
What noise limit applies to data centre diesel generators in India?
75 dB(A) at 1 m from the enclosure surface, for diesel sets up to 1,000 kVA made from 1 January 2005, under CPCB’s noise standard. Compliance comes from an integral acoustic enclosure fitted at manufacture.Central Pollution Control Board
Sources and references.
Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.
- SCC OnlineNew emission standards notified vide Environment (Protection) Third Amendment Rules 2022 ↗
- Commission for Air Quality ManagementDirection on DG sets under GRAP ↗
- Central Pollution Control BoardSystem and procedure for compliance with emission limits for diesel genset engines up to 800 kW ↗
- Central Pollution Control BoardEmission standards for diesel engines above 800 kW ↗
- Central Pollution Control BoardSystem and procedure for compliance with noise limits for diesel generator sets up to 1000 kVA ↗
- Central Pollution Control BoardClassification of sectors into Red, Orange, Green, White and Blue categories (January 2025) ↗
- SEIAA MaharashtraEnvironmental clearance for a Navi Mumbai data centre (21 November 2025) ↗
- PESOFAQs on the Petroleum Rules 2002 (August 2024) ↗
- PESOList of petroleum requiring licence ↗
- Delhi Pollution Control Committee, via National Green TribunalOffice order of 3 June 2025 summarising CAQM directions on DG sets (annexed to its reply in OA 216 of 2026) ↗
- Government of Uttar PradeshUttar Pradesh Data Center Policy 2026 (G.O. dated 9 July 2026) ↗
- Cushman & WakefieldData centre policies in India: a statewise comparison ↗
- Government of Andhra PradeshG.O.Ms.No.17 (Energy), implementation of the CEA safety regulations 2023 (11 March 2026) ↗