A data centre in India that draws groundwater needs a NOC from the Central Ground Water Authority or the state groundwater authority under the guidelines of 24 September 2020, and no new industry other than an MSME gets one in an over-exploited unit. Whether a data centre counts as industry or as infrastructure, which is not barred in over-exploited units, has to be confirmed for each site. Anarock puts water use for cooling-tower data centres at about 25.5 million litres per MW per year. SBI names Bengaluru, Chennai and Gurugram as water-stressed data centre metros, and Uttar Pradesh’s 2026 policy directs data centres to adopt closed-loop systems and treated wastewater reuse.
Before you start
- CGWA 2020 guidelines: NOC needed for groundwater abstraction by industry and infrastructure, with telemetry flow meters, rooftop rainwater harvesting and, above 100 m3 a day for industries, annual water audits.
- Over-exploited units: no NOC for new industries except MSMEs under the CGWA guidelines; 730 of 6,762 units (10.8%) were over-exploited in the 2025 Dynamic Ground Water Resources Assessment.
- Water use: about 25.5 million litres per MW per year for cooling-tower designs (Anarock).
- Karnataka’s 2026-31 policy, as reported by The News Minute, reimburses treated water costs; Uttar Pradesh’s 2026 policy requires a water availability assessment before land allocation in state agency areas.
Groundwater NOC rules for data centres in India
The CGWA guidelines (S.O. 3289(E), 24 September 2020) require all new and existing industries, industries seeking expansion, infrastructure projects and mining projects that abstract groundwater to seek a NOC from CGWA or the state or UT groundwater authority, unless exempt. Exemptions cover domestic users, rural drinking water, the armed forces, agriculture and micro and small enterprises drawing less than 10 m3 a day.Ministry of Jal Shakti, Central Ground Water Authority
| Rule | What the guidelines say |
|---|---|
| Over-exploited units | No NOC for any new industry except MSMEs; expansion that increases abstraction is not permitted |
| Infrastructure projects | Location specific; not barred in over-exploited units, but groundwater for construction only if no treated sewage is available within 10 km |
| Sewage treatment | An STP is mandatory for new projects where groundwater need exceeds 20 m3 a day |
| Metering | Digital water flow meter with telemetry, mandatory for all NOC holders |
| Piezometers | One for 11 to 50 m3 a day; one with a data logger for 51 to 500; two (one with telemetry) above 500 |
| Environmental compensation | ₹20 to ₹200 per m3 for industrial units, depending on the assessment unit category and volume |
Whether a data centre is an industry or an infrastructure project under these guidelines is not settled in the text we reviewed. In an over-exploited unit it decides whether a NOC is possible at all, so put the question to the authority before committing to the site.Ministry of Jal Shakti, Central Ground Water Authority
Water stress in Indian data centre cities
The 2025 Dynamic Ground Water Resources Assessment found 730 of 6,762 assessment units (10.8%) over-exploited. Citizen Matters, citing CGWB’s assessment, reports that all 10 assessment units in Bengaluru Urban and Rural districts are over-exploited, and Newslaundry reported in April 2026 that most of Bengaluru’s data centres sit in its water-stressed areas. Check the category of the unit for a specific site.PIB, Ministry of Jal ShaktiCitizen MattersNewslaundry
SBI names Bengaluru, Chennai and Gurugram as water-stressed data centre metros and notes that newer rules require water management plans.SBI CHAKRA
Water use by data centres in India
Anarock puts water use at about 25.5 million litres per MW per year for Indian data centres with cooling towers.Anarock
The design choice drives the number. The government’s September 2026 explainer says AI infrastructure is driving adoption of direct-to-chip liquid cooling, adiabatic cooling and immersion cooling, and that closed-loop liquid cooling systems are emerging as resource-efficient solutions.PIB
State water rules and incentives for data centres
- Uttar Pradesh (2026): in state agency areas, water availability must be assessed before land is allocated, prior permission or a NOC is needed before using water, and data centres shall adopt water-efficient cooling, closed-loop systems and treated wastewater reuse.
- Karnataka (2026 to 2031): reimburses 100% of treated water charges up to ₹8 lakh a year for 5 years and offers a water usage effectiveness incentive of up to ₹30 lakh a year for 2 years at a WUE of 0.7 to 1.3 litres per kWh, as reported by The News Minute.
- NITI Aayog (October 2026): asks states to verify water capacity before clearing data centre projects.
Operators are moving the same way: Digital Edge announced in February 2026 an 83 MW solar PPA and liquid cooling using 10 million litres of recycled water a day at its BOM campus in Navi Mumbai.Digital Edge
How Invariant helps
Invariant checks groundwater unit status and the water path for an Indian site along with how it gets power, seismic, flood and airport height risk, and maps the approvals. Send the coordinates or the state, the MW and the date you need power.
More on data centres in India
Questions that come up.
Do data centres in India need a CGWA NOC?
Yes, if they draw groundwater. The CGWA guidelines of 24 September 2020 require a NOC from CGWA or the state groundwater authority for industries and infrastructure projects that abstract groundwater, unless exempt.Ministry of Jal Shakti, Central Ground Water Authority
Can a data centre use groundwater in an over-exploited area?
Possibly not. The guidelines bar new industries other than MSMEs from getting a NOC in over-exploited units, while infrastructure projects, being location specific, are not barred. Confirm with the authority how a data centre is treated for the specific site.Ministry of Jal Shakti, Central Ground Water Authority
How much water does a data center use in India?
A data centre in India with cooling towers uses about 25.5 million litres per MW per year, according to Anarock.Anarock
Which Indian cities have water stress for data centres?
SBI names Bengaluru, Chennai and Gurugram as water-stressed data centre metros. Citizen Matters, citing CGWB, reports that all 10 assessment units in Bengaluru Urban and Rural districts are over-exploited.SBI CHAKRACitizen Matters
Do Indian states give incentives for treated water in data centres?
Karnataka’s 2026 policy reimburses treated water charges up to ₹8 lakh a year for 5 years, as reported by The News Minute; Uttar Pradesh’s 2026 policy directs data centres to adopt treated wastewater reuse and requires a water assessment before land allocation in state agency areas.The News MinuteGovernment of Uttar Pradesh
Sources and references.
Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.
- Ministry of Jal Shakti, Central Ground Water AuthorityGuidelines to regulate and control ground water extraction, S.O. 3289(E) of 24 September 2020 ↗
- PIB, Ministry of Jal ShaktiDynamic Ground Water Resources Assessment 2025 ↗
- Citizen MattersWhy Bengaluru needs effective groundwater monitoring ↗
- NewslaundryIn Bengaluru's water-stressed areas sit most of its data centres ↗
- SBI CHAKRAData Centres in India, sector report (April 2026) ↗
- AnarockData Centre: The Blueprint of the Digital Fortress in India (2026) ↗
- PIBData centres in India (explainer, 14 September 2026) ↗
- Government of Uttar PradeshUttar Pradesh Data Center Policy 2026 (G.O. dated 9 July 2026) ↗
- The News MinuteKarnataka's new data centre policy puts water and energy in focus ↗
- ThePrintNITI Aayog asks states to verify power, water capacity before clearing data centre projects ↗
- Digital EdgeDigital Edge India: 83 MW solar PPA and recycled water at its Navi Mumbai campus ↗