Data centres in Noida and Delhi NCR: Greater Noida, YEIDA and Gurugram (2026)

Noida had 156 MW of the 183 MW of operational data centre capacity in Delhi NCR in H1 2026 (Cushman & Wakefield). UP’s 2026 policy and Jewar airport shape new sites.

Delhi NCR had 183 MW of operational data centre capacity in H1 2026, about 10% of India’s top seven cities, according to Cushman & Wakefield, and Noida held 156 MW of it in 12 facilities. NCR is India’s third data centre market on that count, with 360 MW planned; Gurugram has 18 MW. YEIDA lists a 100-acre Data Centre Park in Sector 28 on the Yamuna Expressway. The Uttar Pradesh Data Centre Policy 2026, notified on 9 July 2026, sets the incentives, and Noida International Airport, which began commercial operations on 15 June 2026, has advised that construction within 20 km needs an AAI height clearance.

Before you start

  • Delhi NCR had 183 MW operational, 27 MW under construction and 360 MW planned in H1 2026; Noida had 156 MW and 1,247 MW at early stage (Cushman & Wakefield).
  • UP Data Centre Policy 2026 (G.O. 536/78-2-2026, 9 July 2026): base FAR 3.0 plus 1.0 chargeable, 25% land subsidy in Paschimanchal including Gautam Buddha Nagar, 100% stamp duty exemption on land from government authorities.
  • Delhi is Seismic Zone IV in IS 1893 (Part 1):2002, a higher design load than Mumbai or Chennai.
  • Noida International Airport began commercial operations on 15 June 2026; its July 2025 advisory requires AAI height clearance for construction within 20 km.

Delhi NCR data centre market: key facts (H1 2026)

ItemFigure and period
Operational capacity183 MW in 19 data centres, about 10% of top seven cities (Cushman & Wakefield, H1 2026); 191 MW IT (Savills)
Noida156 MW in 12 data centres; 21 MW under construction; 223 MW planned; 1,247 MW early stage
Gurugram18 MW in 2 data centres
Colocation vacancy10.9% (Cushman & Wakefield, H1 2026)
State policyUP Data Centre Policy 2026, G.O. dated 9 July 2026
LandYEIDA Data Centre Park, Sector 28: 100 acres
Physical risk noteSeismic Zone IV (Delhi, IS 1893 Part 1:2002); Noida International Airport height limits
Cushman & WakefieldCommunications TodayGovernment of Uttar PradeshYamuna Expressway Industrial Development AuthorityBureau of Indian StandardsBusiness Standard

Anarock counts Delhi NCR at 179 MW IT across 18 facilities and forecasts 550 MW by 2030.Anarock

Noida and NCR data centre sub-markets: Noida Expressway, Greater Noida, YEIDA and Gurugram

Anarock’s NCR data centre zones include the Noida Expressway corridor (Sectors 62, 132, 142, 143 and 150 to 167), the Greater Noida corridor (Knowledge Park, Tech Zone, Pari Chowk), the Yamuna Expressway and Jewar corridor under YEIDA, and the Gurugram-Manesar belt. Its project list includes Yotta’s Greater Noida campus, NTT in Sector 142, STT GDC in Sector 143, Sify in Sector 132 and AdaniConneX in Sectors 62 and 80. Yotta lists 30 MW of IT load at its D1 building in Greater Noida.AnarockYotta

YEIDA lists a 100-acre Data Centre Park in Sector 28, the same sector as its Medical Devices Park. AdaniConneX lists 150 MW of potential capacity in Noida, and AM Green signed an MoU with Uttar Pradesh in January 2026 for a 1 GW AI data centre in the Greater Noida region, with first capacity targeted for 2028.Yamuna Expressway Industrial Development AuthorityAdaniConneXCommunications Today

UP Data Centre Policy 2026: subsidies, FAR and power incentives

Uttar Pradesh notified its Data Centre Policy 2026 by G.O. 536/78-2-2026 dated 9 July 2026, repealing the 2021 policy. Parks are 40 MW or more; units are above 2 MW and below 40 MW. Parks get an interest subsidy with an overall ceiling of Rs 50 crore and a dual-grid subsidy; units get a capital subsidy with a ceiling of Rs 20 crore. Booster incentives can raise both ceilings.Government of Uttar PradeshInvest UP

  • Land subsidy of 25% of prevailing sector rates on land from state agencies in Madhyanchal and Paschimanchal; Gautam Buddha Nagar is listed in Paschimanchal.
  • 100% stamp duty exemption on purchase or lease from a government authority, against a bank guarantee released at commencement of commercial operation.
  • Base FAR 3.0 free plus 1.0 chargeable; basement parking, storage and DG set space sit outside FAR, rooftop chillers can be installed without counting in FAR, and ground coverage is up to 60% or as per byelaws.
  • Units get a 100% electricity duty exemption for 10 years. Wheeling and transmission charges on intrastate purchase are 50% exempt (75% for renewable power from within the state), and 100% exempt on the intrastate system for interstate purchase, for 25 years, until the first eight parks or 2 GW.
  • Data centres are classified as an essential service under ESMA, and the state agency assesses water availability before allotting land.
Government of Uttar Pradesh

Gurugram and Manesar are in Haryana, so Uttar Pradesh’s terms do not apply there. Compare both states’ terms for an NCR search; the right answer depends on load size and the power route.

Power and water for data centres in Noida and NCR

Under the UP Supply Code, contracted loads above 10,000 kVA are supplied at 132 kV or 220 kV, and supply on an independent feeder depends on technical feasibility and bay or corridor availability at the substation. UPERC’s FY 2026-27 order prices HV-2 large and heavy power, which covers IT and ITeS units decided by the state through a policy notification, at Rs 6.10 per kVAh above 132 kV and Rs 6.40 above 66 kV up to 132 kV in urban areas, plus Rs 270 per kVA per month.DVVNLUttar Pradesh Electricity Regulatory Commission

The UP policy reimburses the cost of one grid in a dual-grid connection for parks and cuts wheeling and transmission charges, which matters for green open access contracts. Ask for the specific substation and the DISCOM’s sanction letter; sector-level claims of available power do not tell you what is left for a new load.Government of Uttar Pradesh

Groundwater is a harder constraint. CGWA guidelines bar groundwater NOCs for new industries other than MSMEs in over-exploited assessment units, and SBI lists Gurugram among the water-stressed data centre metros. Plan for treated wastewater or air and closed-loop cooling.Central Ground Water Authority, Ministry of Jal ShaktiSBI CHAKRA Centre of Excellence

Data centre site risks in Noida and NCR

  • Seismic: Delhi is Zone IV (zone factor 0.24) in the IS 1893 (Part 1):2002 town list, a higher design load than Mumbai, Chennai or Hyderabad. Confirm the zone for the specific YEIDA sector.
  • Airport: Noida International Airport at Jewar began commercial operations on 15 June 2026. In July 2025 the airport advised that no construction or tree planting proceed within 20 km without a height clearance or NOC from AAI.
Bureau of Indian StandardsBusiness StandardThePrint (PTI)

Invariant checks the evidence behind a site’s power (the DISCOM or transmission connection, the open access route, the nearest substations and what else is queued on them), screens seismic zone, flood history, groundwater status and airport height limits, and lists the central and state approvals the project needs with the authority behind each one. In NCR the groundwater unit and the Jewar height surface are checked alongside the power route.

More on data centres in India

Questions that come up.

How much data centre capacity does Noida have?

Noida had 156 MW of operational data centre capacity in H1 2026, out of 183 MW across Delhi NCR, according to Cushman & Wakefield. Another 1,247 MW was at early stage in Noida.Cushman & Wakefield

What is the YEIDA data centre park?

The YEIDA Data Centre Park is a 100-acre site in Sector 28 on the Yamuna Expressway. YEIDA lists it in its available land bank alongside its Medical Devices Park in the same sector.Yamuna Expressway Industrial Development Authority

What incentives does the UP Data Centre Policy 2026 offer?

The UP Data Centre Policy 2026 offers capital and interest subsidies, land and stamp duty concessions, and electricity duty and wheeling and transmission charge exemptions. Parks get an interest subsidy with a Rs 50 crore ceiling and units a capital subsidy with a Rs 20 crore ceiling. Land from state agencies in Madhyanchal and Paschimanchal gets a 25% subsidy, land from government authorities a 100% stamp duty exemption, and units 10 years of electricity duty exemption.Government of Uttar PradeshInvest UP

Is Noida a good location for a data center?

Noida offers proximity to the national capital, extensive fibre connectivity and access to large development land, according to Anarock, and the UP policy adds incentives. The site checks are groundwater, Seismic Zone IV design and height limits near the new Jewar airport.AnarockGovernment of Uttar PradeshBureau of Indian StandardsThePrint (PTI)

Which companies run data centres in Noida?

Anarock lists Yotta, NTT, STT GDC, Sify and AdaniConneX projects in Noida and Greater Noida. AM Green has an MoU for a 1 GW AI data centre in the Greater Noida region.AnarockCommunications Today

Do I need an AAI height clearance near Noida International Airport?

Yes, within 20 km of the airport. In July 2025 Noida International Airport advised that no construction or tree planting proceed within 20 km without a height clearance or NOC from AAI. The airport began commercial operations on 15 June 2026.ThePrint (PTI)Business Standard

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. Cushman & WakefieldIndia Data Centre Market Overview H1 2026 ↗
  2. Communications TodayIndia's data centre capacity additions jump 59% in H1 2026 (Savills India) ↗
  3. Government of Uttar PradeshUttar Pradesh Data Centre Policy 2026 (G.O. 536/78-2-2026, 9 July 2026) ↗
  4. Yamuna Expressway Industrial Development AuthorityIndustrial property and Data Centre Park, Sector 28 ↗
  5. Bureau of Indian StandardsIS 1893 (Part 1):2002, criteria for earthquake resistant design, Annex E zone factors ↗
  6. Business StandardCommercial operations begin at Noida International Airport ↗
  7. AnarockData Centre: The Blueprint of the Digital Fortress in India (2026) ↗
  8. YottaData centers in India ↗
  9. AdaniConneXData centers ↗
  10. Communications TodayUttar Pradesh signs MoU with AM Green Group for 1 GW AI data centre ↗
  11. Invest UPUttar Pradesh Data Centre Policy 2026 ↗
  12. DVVNLUP Electricity Supply Code 2005: salient features ↗
  13. Uttar Pradesh Electricity Regulatory CommissionUPPCL tariff order FY 2026-27 (2 July 2026) ↗
  14. Central Ground Water Authority, Ministry of Jal ShaktiGuidelines to regulate and control ground water extraction in India (24 September 2020) ↗
  15. SBI CHAKRA Centre of ExcellenceData Centres in India: sector report (April 2026) ↗
  16. ThePrint (PTI)Height restrictions put in place within 20 km radius of Noida airport ↗