Data centre site due diligence in India starts with power: whether the parcel can get the full load, at the voltage needed, on a date you can underwrite. After power come title and land use, groundwater (under the 2020 CGWA guidelines no new industry other than MSMEs gets a groundwater permit in an over-exploited unit), seismic zone under IS 1893, flood and cyclone history from IMD records, AAI height limits within 20 or 56 km of an airport, and the approvals path. NITI Aayog’s October 2026 framework now asks states to verify power and water capacity before clearing data centre projects, so the state will ask the same questions.
Before you start
- Power evidence is graded by the document: a written connection offer or sanctioned load beats proximity to a substation.
- Groundwater: check the site’s assessment unit category; 730 of 6,762 units (10.8%) were over-exploited in the 2025 Dynamic Ground Water Resources Assessment.
- Seismic: design to IS 1893 (Part 1):2016; BIS lists the 2025 edition of Part 1 as withdrawn.
- Airports: under G.S.R. 751(E) of 2015, AAI height clearance is needed within 20 km of VFR and 56 km of IFR airports; it is valid 8 years and has no fee.
Data centre site due diligence checklist for India
| Check | What to obtain | Where it comes from | Why it matters |
|---|---|---|---|
| Power | Serving utility, voltage, MW, date, and the substation and line it depends on | Discom or state transmission utility, in writing | Sets the schedule; Navi Mumbai’s data centre allocation is reported close to fully committed |
| Title and encumbrances | Clear title chain and encumbrance search | State land records and sub-registrar | A defect blocks financing and allotment transfers |
| Land use and building norms | Permitted use, FAR, ground coverage, height | Development authority, allotment terms, state data centre policy | Decides how many MW fit; UP 2026 allows FAR 3.0 plus 1.0 |
| Groundwater | Assessment unit category and whether a NOC is possible | CGWB assessment; CGWA or state groundwater authority | Over-exploited units bar new industries other than MSMEs |
| Seismic | Zone and zone factor | IS 1893 (Part 1) | Structural cost; zone IV in Delhi, III in Mumbai and Chennai |
| Flood and cyclone | Record rainfall, flood events, cyclone tracks near the site | IMD records; BMTPC Vulnerability Atlas | Plinth level, drainage, generator and fuel siting |
| Coastal zone | Distance from the high tide line | CRZ Notification 2019 and the approved coastal zone management plan | No Development Zones of 50 m or 200 m in CRZ-III |
| Airport height | Permissible top elevation | AAI NOCAS and colour coded zoning maps | Caps building and stack height near Navi Mumbai and Noida |
| Environmental clearance | Whether built-up area crosses 20,000 sq m | EIA Notification 2006 item 8(a) | Adds a state appraisal before construction |
| Policy eligibility | Which incentives are open and their conditions | Notified state policy text | Tamil Nadu’s 2021 policy lapsed and Uttar Pradesh’s was replaced in 2026 |
Power evidence for a data centre site in India
Power due diligence on an Indian site tests the document behind the MW, not the distance to a substation: a parcel near a 220 kV substation is not a 100 MW site until the utility has said, in writing, how much it can supply and when, and what upgrades that depends on. Crisil estimates that by FY2030 data centre capacity could equal about 60% of Mumbai’s current peak demand and about 80% of Visakhapatnam’s.Deccan Herald
Groundwater rules for a data centre site
Under the CGWA guidelines of 24 September 2020, any new or expanding industry or infrastructure project that abstracts groundwater needs a NOC unless exempt, and no new industry other than MSMEs gets one in an over-exploited unit. Infrastructure projects are treated as location specific and are not barred outright. Whether a data centre is treated as industry or infrastructure is not settled in the guidelines’ text, so confirm it with the authority for the specific site.Ministry of Jal Shakti, Central Ground Water Authority
The 2025 national assessment classed 730 of 6,762 units (10.8%) as over-exploited. Citizen Matters, citing CGWB’s assessment, reports that all 10 assessment units in Bengaluru Urban and Rural districts are over-exploited.PIB, Ministry of Jal ShaktiCitizen Matters
Seismic zone, flood, cyclone and coastal zone checks
The IS 1893 (Part 1):2002 town list puts Delhi in zone IV, Mumbai, Chennai, Pune, Kolkata and Ahmedabad in zone III, and Bengaluru, Hyderabad and Visakhapatnam in zone II. Flood records to check against include 944 mm on 26 July 2005 in Mumbai, a 24-hour record for the city, and 1,178.3 mm in November 2015 at Chennai’s Meenambakkam. Cyclone Hudhud crossed the coast over Visakhapatnam on 12 October 2014 with maximum sustained winds of about 180 km/h and a 1.4 m storm surge.Bureau of Indian StandardsNOAA National Centers for Environmental InformationIndia Meteorological Department, RMC ChennaiIndia Meteorological Department
Near the coast, the CRZ Notification 2019 sets a No Development Zone of 200 m from the high tide line in CRZ-IIIB, and of 50 m in CRZ-IIIA (rural areas with more than 2,161 people per sq km) once the coastal zone management plan under the 2019 notification is approved; until then 200 m continues to apply.Ministry of Environment, Forest and Climate Change
AAI airport height clearance for data centres
Under G.S.R. 751(E) of 2015, a data centre needs a height clearance from AAI within 20 km of an airport operating under visual flight rules and 56 km of one under instrument flight rules. The clearance is valid for 8 years and has no fee. Navi Mumbai International Airport began commercial flights on 25 December 2025 and Noida International Airport on 15 June 2026; Noida International Airport issued an advisory in July 2025 that no construction should take place within 20 km of it without an AAI height clearance.Airports Authority of IndiaBusiness StandardBusiness StandardThePrint (PTI)
How Invariant helps
Invariant runs this checklist on Indian sites: it checks how the site gets power and the evidence behind the MW, screens seismic zone, flood and cyclone history, groundwater status and airport height limits, and maps the central and state approvals with the authority behind each. Send the coordinates or the state, the MW and the date you need power.
More on data centres in India
Questions that come up.
What does data centre site due diligence cover in India?
It is a structured check of whether a parcel can become a data centre on your timeline: power evidence, title and land use, water, seismic, flood and cyclone risk, airport height limits and the approvals path.Airports Authority of IndiaMinistry of Jal Shakti, Central Ground Water AuthorityBureau of Indian Standards
What should a data centre site selection checklist in India include?
Power (utility, voltage, MW, date, in writing), title and encumbrances, land use and FAR, groundwater unit status, seismic zone, flood and cyclone records, coastal zone limits, airport height clearance, environmental clearance threshold and state policy eligibility.Ministry of Jal Shakti, Central Ground Water AuthorityBureau of Indian StandardsMinistry of Environment, Forest and Climate ChangeAirports Authority of IndiaMinistry of Environment and Forests
How do I check if groundwater can be used at a site in India?
Find the category of the site’s assessment unit in CGWB’s latest assessment. In over-exploited units the 2020 CGWA guidelines bar new industries other than MSMEs from getting a groundwater NOC, while infrastructure projects, being location specific, are not barred.Ministry of Jal Shakti, Central Ground Water Authority
Do I need AAI height clearance for a data centre?
Yes, if the site is within 20 km of a VFR airport or 56 km of an IFR airport. In cities with a colour coded zoning map, local bodies can approve buildings below the permissible top elevation without referring to AAI. Clearance is valid for 8 years and has no fee.Airports Authority of India
What is a data center feasibility study in India?
A first pass over the same checklist, run before land is bought: whether power can be had at the needed MW and date, whether the land and water work, and which physical risks and approvals apply. It ends in a go, no-go or conditional go.
Sources and references.
Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.
- Structure ResearchMumbai and Pune data centre report 2026 ↗
- Government of Uttar PradeshUttar Pradesh Data Center Policy 2026 (G.O. dated 9 July 2026) ↗
- Ministry of Jal Shakti, Central Ground Water AuthorityGuidelines to regulate and control ground water extraction, S.O. 3289(E) of 24 September 2020 ↗
- Bureau of Indian StandardsIS 1893 (Part 1):2002, criteria for earthquake resistant design, Annex E ↗
- India Meteorological Department, RMC ChennaiMeenambakkam extremes and normals ↗
- Building Materials and Technology Promotion CouncilVulnerability Atlas of India, third edition (2019) ↗
- Ministry of Environment, Forest and Climate ChangeCRZ Notification 2019, G.S.R. 37(E) of 18 January 2019 (copy hosted by the Government of Puducherry) ↗
- Airports Authority of IndiaNOCAS frequently asked questions (height clearance) ↗
- Ministry of Environment and ForestsEIA Notification 2006 ↗
- Government of Tamil Nadu (via National Single Window System)Tamil Nadu Data Centre Policy 2021 ↗
- Deccan HeraldIndia set for five times surge in its data centre capacity by 2030 (Crisil Ratings, 3 November 2026) ↗
- PIB, Ministry of Jal ShaktiDynamic Ground Water Resources Assessment 2025 ↗
- Citizen MattersWhy Bengaluru needs effective groundwater monitoring ↗
- NOAA National Centers for Environmental InformationGlobal hazards and significant events, July 2005 (archived copy) ↗
- India Meteorological DepartmentVery severe cyclonic storm Hudhud: a report ↗
- Business StandardNavi Mumbai airport begins commercial flight operations (25 December 2025) ↗
- Business StandardCommercial operations begin at Noida International Airport ↗
- ThePrint (PTI)Height restrictions put in place within 20 km radius of Noida airport (PTI, 12 July 2025) ↗