India had roughly 1.8 GW of operational data centre capacity in H1 2026 (Cushman & Wakefield and Savills) and Singapore about 1.4 GW in 2024 (EDB). Malaysia’s utility TNB had signed supply agreements for 8.3 GW of data centre projects by July 2026 (RHB Research), though the three figures are not like for like. Singapore releases new capacity through allocation calls; its second call, in December 2025, offered at least 200 MW. Johor introduced a higher water tariff for data centres in August 2025. India offers build costs that Cushman & Wakefield puts about 23% below Malaysia, and a tax holiday to 2047 for foreign cloud companies using Indian data centres.
Before you start
- Singapore: capacity is allocated, not open. DC-CFA2 (launched 1 December 2025) offered at least 200 MW with PUE 1.25 at full load, Green Mark Platinum and at least 50% green energy pathways.
- Malaysia: TNB had 59 data centre projects and 8.3 GW under electricity supply agreements by July 2026 (RHB Research). Johor has a state technical committee that evaluates data centre projects for water impact, and set a data centre water tariff from 1 August 2025.
- India: build cost about US$7.4 million per MW (Cushman & Wakefield), rents 30 to 35% below peer markets (Crisil), and 11 states with dedicated data centre policies.
- The capacity figures are not like for like: Singapore’s 1.4 GW is a 2024 figure published by EDB, Malaysia’s 8.3 GW is capacity under TNB supply agreements, and India’s 1.8 GW is operational capacity from market reports.
India, Singapore and Johor data centre markets side by side
| Measure | India | Singapore | Johor (Malaysia) |
|---|---|---|---|
| Capacity figure | About 1.8 GW operational, H1 2026 (Cushman & Wakefield 1,789 MW, top seven cities; Savills 1,819 MW IT) | About 1.4 GW across more than 70 data centres (EDB, May 2024) | TNB supply agreements: 59 projects, 8.3 GW; 36 completed with 4.5 GW maximum capacity (RHB via The Star, July 2026). Malaysia-wide |
| How new capacity is released | No national allocation; 11 states have dedicated data centre policies | Allocation calls: 80 MW secured through a pilot call in 2023; DC-CFA2 for at least 200 MW (December 2025) | TNB electricity supply agreements; a Johor state technical committee evaluates and approves data centre projects |
| Efficiency condition | SBI’s sector report says MeitY AI cloud tenders have required PUE below 1.35 | DC-CFA2: PUE 1.25 or better at full IT load; Green Mark for Data Centres 2024 Platinum | Johor committee considers water efficiency and recommends water-saving cooling |
| Green power condition | State-specific, for example at least 51% green power in Maharashtra’s green data centre parks and under Gujarat’s 2026-29 policy | At least 50% of new capacity via eligible green pathways (DC-CFA2) | Not covered here |
| Water | CGWA guidelines bar groundwater NOCs for new industries (other than MSMEs) in over-exploited units | Not covered here | Data centre water tariff of RM5.33 per cubic metre from 1 August 2025 |
| Build cost | About US$7.4 million per MW, about 23% below Malaysia (Cushman & Wakefield) | Not compared here | India is about 23% below Malaysia (Cushman & Wakefield, country level; no Johor figure) |
| Tax | Tax holiday from tax year 2026-27 to 2046-47 for foreign cloud companies serving global customers using Indian data centre services (Budget 2026-27) | Not compared here | Not compared here |
Singapore: data centre capacity by allocation call, with strict conditions
Singapore releases new data centre capacity through allocation calls. It imposed a moratorium on new data centres in 2019 and relaxed it through a pilot call for applications launched in July 2022, under which operators secured 80 MW in 2023. Its Green Data Centre Roadmap, launched on 30 May 2024, set out at least 300 MW of additional capacity in the next few years and another 200 MW for operators using green energy. The second Data Centre Call for Application opened on 1 December 2025 for at least 200 MW and its application window closed on 31 March 2026.Morgan LewisSingapore Economic Development BoardNorton Rose Fulbright
Selected applicants must reach PUE of 1.25 or better at full design load, obtain Green Mark for Data Centres 2024 Platinum, and power at least half of the new capacity through eligible green pathways such as biomethane, low-carbon hydrogen or ammonia, or building-integrated solar. Morgan Lewis notes that land scarcity and strict controls have led global tech firms to look to alternatives such as Johor.Norton Rose FulbrightMorgan Lewis
Malaysia and Johor: TNB power agreements and water rules
Malaysia’s utility TNB had electricity supply agreements for 59 data centre projects with a combined 8.3 GW, of which 36 projects with a maximum capacity of 4.5 GW were completed, according to RHB Research as reported by The Star in July 2026. These are Malaysia-wide figures under supply agreements, not a measure of IT load in use.The Star
Water is a stated concern in Johor. In August 2025 the state said it was the only state with a technical committee dedicated to evaluating and approving data centre projects, particularly their impact on water resources, amid concerns about a possible treated water shortfall by 2030. A data centre water tariff of RM5.33 per cubic metre took effect on 1 August 2025.Malay MailThe Star
India: lower build cost, state-by-state rules
Building a data centre in India costs about US$7.4 million per MW, about 23% below Malaysia and 26% below Australia, according to Cushman & Wakefield, and Crisil reports Indian rents 30 to 35% below peer markets. The Budget 2026-27 tax holiday to 2047 applies to foreign companies serving global customers using data centre services in India.Invest India and Cushman & WakefieldDeccan HeraldPress Information Bureau
The trade-offs include grid allocation and state-by-state rules. There is no notified national data centre policy, and states set their own incentives. Structure Research reports that committed capacity is approaching MSEDCL’s data centre grid allocation in Navi Mumbai, pushing new Mumbai builds to Panvel, Taloja and Rasayani. Beyond Mumbai, Hyderabad holds 18% of upcoming supply and Cushman & Wakefield maps more than 4 GW of early-stage or announced capacity at Visakhapatnam.S&R AssociatesStructure ResearchCushman & WakefieldInvest India and Cushman & Wakefield
More on data centres in India
Questions that come up.
Is India cheaper than Singapore for data centres?
The sources here give no direct Singapore cost figure, but India’s costs are low against regional peers. Cushman & Wakefield puts construction at about US$7.4 million per MW, about 23% below Malaysia, and Crisil reports Indian rents 30 to 35% below peer markets. New Singapore capacity is released through allocation calls with strict efficiency and green power conditions.Invest India and Cushman & WakefieldDeccan HeraldNorton Rose Fulbright
How much data centre capacity does India have compared with Singapore?
India had roughly 1.8 GW of operational capacity in H1 2026, on Cushman & Wakefield’s 1,789 MW for the top seven cities and Savills’ 1,819 MW of IT load. Singapore had about 1.4 GW in May 2024, according to EDB.Cushman & WakefieldCommunications TodaySingapore Economic Development Board
How much data centre capacity does Singapore have?
Singapore had about 1.4 GW across more than 70 data centres, according to the Singapore Economic Development Board in May 2024. Its Green Data Centre Roadmap sets out at least 300 MW more in the next few years.Singapore Economic Development Board
What water rules apply to data centres in Johor?
Johor has charged data centres a water tariff of RM5.33 per cubic metre since 1 August 2025. A state technical committee also evaluates and approves data centre projects, particularly their impact on water resources.Malay MailThe Star
What is Singapore’s DC-CFA2?
DC-CFA2 is Singapore’s second Data Centre Call for Application, launched on 1 December 2025 to allocate at least 200 MW. Applicants must meet PUE 1.25 at full load, Green Mark for Data Centres 2024 Platinum and at least 50% green energy pathways.Norton Rose FulbrightMorgan Lewis
Does India have a data center tax incentive for foreign cloud companies?
Yes. Budget 2026-27 introduced a tax holiday from tax year 2026-27 to 2046-47 for foreign companies providing cloud services globally using data centre services from India, with sales to Indian users through an Indian reseller.Press Information Bureau (MeitY)Press Information Bureau
Sources and references.
Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.
- Cushman & WakefieldIndia Data Centre Market Overview H1 2026 ↗
- Communications TodayIndia's data centre capacity additions jump 59% in H1 2026 (Savills India) ↗
- Singapore Economic Development BoardSingapore to expand data centre capacity by at least one third, pushes for green energy use ↗
- Morgan LewisSingapore announces data center capacity allocation call ↗
- Norton Rose FulbrightSingapore’s Green Data Centre Roadmap and DC-CFA2 ↗
- The StarData centre demand to energise TNB growth ↗
- Malay MailJohor govt sets up special committee to vet data centres’ impact on water demand ↗
- The StarJohor’s water tariff adjustment: data centres would have to pay more ↗
- SBI CHAKRA Centre of ExcellenceData Centres in India: sector report (April 2026) ↗
- International Bar AssociationGreen data centres in India: policy meets practice ↗
- Central Ground Water Authority, Ministry of Jal ShaktiGuidelines to regulate and control ground water extraction in India (24 September 2020) ↗
- Invest India and Cushman & WakefieldIndia's Data Centre Growth Story (October 2026) ↗
- Press Information BureauBackgrounder: tax holiday for foreign cloud companies using Indian data centres ↗
- Deccan HeraldIndia set for five times surge in its data centre capacity by 2030 (Crisil Ratings) ↗
- Structure ResearchMumbai and Pune data centre report 2026 ↗
- Press Information Bureau (MeitY)Union Budget 2026-27: cloud and data centre measures ↗
- S&R AssociatesIndian Budget 2026-27: tax incentives for data centres ↗