Data centres in Mumbai and Navi Mumbai: capacity, sub-markets and power (2026)

Mumbai had 890 MW of operational data centre capacity in H1 2026, most of it on Thane-Belapur Road in Navi Mumbai, where grid allocation is now the constraint.

Mumbai had 890 MW of operational data centre capacity in H1 2026, about 50% of India’s top seven cities, according to Cushman & Wakefield. That makes Mumbai India’s largest data centre market, and the same count shows 281 MW under construction and 1,445 MW planned. Thane-Belapur Road in Navi Mumbai holds 675 MW of it, and the city has 13 cable landing stations. Structure Research reports that MSEDCL has allocated about 6 GW of grid capacity to Navi Mumbai data centres, that committed and under-construction capacity is approaching that figure, and that new builds are moving to Panvel, Taloja and Rasayani.

Before you start

  • Mumbai had 890 MW operational, 281 MW under construction and 1,445 MW planned in H1 2026, according to Cushman & Wakefield. Savills counts 846 MW of IT load, 46% of India.
  • Thane-Belapur Road holds 675 MW of Mumbai’s capacity at 4.4% colocation vacancy, and Powai holds 176 MW (Cushman & Wakefield, H1 2026). Structure Research reports new builds moving to Panvel, Taloja and Rasayani.
  • Structure Research reports that committed capacity is approaching the roughly 6 GW grid allocation for Navi Mumbai data centres, so power evidence is the first check on any Mumbai site.
  • Navi Mumbai International Airport began commercial operations on 25 December 2025.

Mumbai data centre market: key facts (H1 2026)

ItemFigure and period
Operational capacity890 MW, about 50% of the top seven cities (Cushman & Wakefield, H1 2026); 846 MW IT, 46% of India (Savills, H1 2026)
Under construction and planned281 MW under construction; 1,445 MW planned (Cushman & Wakefield, H1 2026)
Share of upcoming supply45% of 3,860 MW upcoming in the top seven cities, H2 2026 to 2030 (Cushman & Wakefield)
Colocation vacancy7.9% city-wide; 4.4% on Thane-Belapur Road (Cushman & Wakefield, H1 2026)
Facilities54 data centres (Cushman & Wakefield, H1 2026)
Cable landing stations13, with 2 more scheduled for completion in 2026 (Cushman & Wakefield)
State policyMaharashtra IT/ITES Policy 2023 data centre incentives; Integrated Green Data Centre Parks, expanded from 3 to 20 parks by a June 2026 GR (Fox Mandal, via the International Bar Association)
Grid noteAbout 6 GW allocated by MSEDCL to Navi Mumbai data centres, with committed capacity approaching it (Structure Research, 2026)
Physical risk noteSeismic Zone III (IS 1893 Part 1:2002); 944 mm of rain on 26 July 2005, a 24-hour record for the city (NOAA)
Cushman & WakefieldCommunications TodayStructure ResearchCyril Amarchand MangaldasInternational Bar AssociationBureau of Indian StandardsNOAA National Centers for Environmental Information

Mumbai capacity estimates differ by method. Cushman & Wakefield counts colocation and hyperscale cloud capacity in the top seven cities. Savills counts IT load. Anarock gives 812 MW IT across 54 facilities for Mumbai-MMR. Use one publisher consistently when comparing periods.Cushman & WakefieldCommunications TodayAnarock

Mumbai took about 83% of capacity added across the top seven cities in H1 2026 (148 MW), and Cushman & Wakefield expects the city to cross 1 GW of operational capacity by the end of 2026. According to Tele.net, the Mumbai Metropolitan Region handles around 95% of India’s international bandwidth.Cushman & WakefieldTele.net

Mumbai data centre sub-markets: Thane-Belapur Road, Powai, Panvel, Taloja and Palava

Sub-marketOperationalVacancyPipeline
Thane-Belapur Road675 MW in 35 data centres4.4%241 MW under construction, 995 MW planned, 2,286 MW early stage
Powai176 MW in 31 data centres13.1%40 MW under construction, 185 MW planned, 171 MW early stage
Panvel22 MW in 2 data centres56.4%75 MW planned, 75 MW early stage
Cushman & Wakefield

Anarock describes Navi Mumbai (Airoli, Ghansoli, Rabale, Mahape and Panvel) as the largest concentration of hyperscale and colocation data centres, and the Chandivali and Powai-Andheri (E) corridor as a major interconnection hub. Equinix opened MB3 in Chandivali, Powai, in April 2026 with an initial investment of over US$95 million. Anarock names Dombivali and Taloja as an emerging lower-cost hyperscale corridor.AnarockEquinix

Yotta’s NM1 at Panvel has 52 MW of IT load in a park it says can scale to 1 GW. AdaniConneX lists 1,000 MW of potential capacity in Navi Mumbai, and CoreWeave plans a 240 MW deployment at AdaniConneX’s Taloja campus, with the first phase expected in mid-2028. Digital Edge plans a 400 MW Navi Mumbai campus. STT GDC broke ground at Palava with an initial 50 MW on 46 acres, designed to scale to about 400 MW.YottaAdaniConneXCoreWeaveDigital EdgeW.Media

Power for Mumbai data centres: the Navi Mumbai grid allocation

Structure Research reports that MSEDCL has allocated about 6 GW of grid capacity to data centres in Navi Mumbai and that committed and under-construction capacity is approaching that figure. New builds are moving to Panvel, Taloja and Rasayani, where separate substations can be commissioned. The same report notes a Maharashtra framework from October 2025 that lets data centre parks generate and distribute their own power.Structure Research

Crisil Ratings estimates that by fiscal 2030 data centre capacity in Mumbai could equal about 60% of the city’s current peak power demand. That is the scale problem a new site has to answer: a firm date for a large load needs a named substation, a transmission plan and a connection agreement.Deccan Herald

Under MERC’s Supply Code, 33 kV supply covers contract demand up to 10,000 kVA, or 20,000 kVA in a Metropolitan Area or on an express feeder; larger loads connect at extra high voltage. A connection that needs a new distribution substation has a one-year standard. Multiple sources of supply can be provided if the consumer asks and it is technically feasible, with the extra cost borne by the consumer.Maharashtra Electricity Regulatory Commission (via MSEDCL)

MERC’s March 2025 tariff order classified data centres in the industrial category, with the same rebates and incentives, and approved a 10% discount in wheeling charges for data centres on 100% green power. Construction World reported in October 2025 that the state industries department had notified 25 areas in Kurla, Chandivali, Marol, Thane, Navi Mumbai and Panvel as designated data centre parks and units with deemed distribution licences.Maharashtra Electricity Regulatory CommissionConstruction World

Maharashtra’s IT/ITES Policy 2023 gives new data centre units outside Zone I a Rs 1 per unit tariff subsidy for 5 years, and a notification of 22 June 2026 exempts data centre units from electricity duty for 20 years. According to a Fox Mandal analysis published by the International Bar Association, a June 2026 government resolution amended the Integrated Green Data Centre Parks policy: at least 51% green power for core operations, and a Rs 1 per unit tariff subsidy for 10 or 20 years depending on investment size.Cyril Amarchand MangaldasGovernment of Maharashtra (gazette copy via Simpliance)International Bar Association

Data centre land prices and approvals in Mumbai

Anarock benchmarks land at Rs 35 to 60 crore per acre for 5 to 10 MW facilities in Mumbai-MMR suburbs and Rs 3 to 10 crore per acre for 100 to 500 MW parks in locations such as Navi Mumbai. Recent deals show the spread. Communications Today reported that STT GDC paid Rs 282 crore for a 14,093 sq m plot (about 3.5 acres) with an existing building in the TTC Industrial Area in May 2026. DCD reported in 2024 that AWS bought 38.18 acres from Lodha at Palava for more than Rs 450 crore.AnarockCommunications TodayDCD

Building approvals include state environmental clearance. Nxtra’s Mahape expansion in the TTC Industrial Area, with two data centre buildings, two generator buildings and a substation building and 76,930 sq m of total built-up area, received its clearance from SEIAA Maharashtra on 21 November 2025.SEIAA Maharashtra

Maharashtra’s IT/ITES Policy 2023 gives a 100% stamp duty exemption on land or premises for new or expanded data centres and allows data centres in any zone.Cyril Amarchand Mangaldas

Data centre site risks in Mumbai: seismic zone, flooding and airport height limits

  • Seismic: Mumbai and Thane are Zone III (zone factor 0.16) in the IS 1893 (Part 1):2002 town list.
  • Flood: 944 mm of rain fell on Mumbai on 26 July 2005, breaking the city’s 24-hour record and causing massive flooding (NOAA). Low-lying plots need a site-level drainage and flood check.
  • Airports: AAI height NOCs apply up to 20 km from VFR airports and 56 km from IFR airports, measured from the aerodrome reference point; where a colour-coded zoning map exists, local bodies can approve heights below its limit. Navi Mumbai International Airport began commercial operations on 25 December 2025.
Bureau of Indian StandardsNOAA National Centers for Environmental InformationAirports Authority of IndiaBusiness Standard

Invariant checks the evidence behind a site’s power (the DISCOM or transmission connection, the open access route, the nearest substations and what else is queued on them), screens seismic zone, flood history, groundwater status and airport height limits, and lists the central and state approvals the project needs with the authority behind each one. In Mumbai the first question is which substation serves the plot and how much of its allocation is already committed.

More on data centres in India

Questions that come up.

How much data centre capacity does Mumbai have?

Mumbai had 890 MW of operational data centre capacity in H1 2026, about half of India’s top seven cities, according to Cushman & Wakefield. The same count shows 281 MW under construction and 1,445 MW planned. Savills counted 846 MW of IT load.Cushman & WakefieldCommunications Today

Where are the data centres in Navi Mumbai?

Most Navi Mumbai data centre capacity is on Thane-Belapur Road, which holds 675 MW according to Cushman & Wakefield. Structure Research reports new builds moving to Panvel, Taloja and Rasayani, and STT GDC has broken ground at Palava, in the wider Mumbai region outside Navi Mumbai.Cushman & WakefieldStructure ResearchW.Media

Is power a constraint for data centres in Navi Mumbai?

Yes. Structure Research reports that committed and under-construction capacity is approaching the roughly 6 GW grid allocation for Navi Mumbai data centres, and new builds are moving to locations where separate substations can be commissioned.Structure Research

Why is Mumbai India’s biggest data center market?

Cushman & Wakefield attributes Mumbai’s lead to its 13 cable landing stations, with two more due in 2026, power availability and fibre connectivity. Tele.net reports that the region handles around 95% of India’s international bandwidth.Cushman & WakefieldTele.net

How much does data centre land cost in Mumbai?

Anarock puts land for 5 to 10 MW facilities in the Mumbai-MMR suburbs at Rs 35 to 60 crore per acre, and land for 100 to 500 MW parks in locations such as Navi Mumbai at Rs 3 to 10 crore per acre. Individual deals vary with the buildings and power on the plot.Anarock

Which companies are building data centres in Navi Mumbai?

Yotta, AdaniConneX, CoreWeave, Digital Edge and STT GDC have projects in Navi Mumbai and the wider Mumbai region. Yotta’s NM1 at Panvel has 52 MW of IT load; CoreWeave plans a 240 MW deployment at AdaniConneX’s Taloja campus, with the first phase expected in mid-2028; Digital Edge plans a 400 MW campus; and STT GDC broke ground at Palava with an initial 50 MW.YottaAdaniConneXCoreWeaveDigital EdgeW.Media

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. Cushman & WakefieldIndia Data Centre Market Overview H1 2026 ↗
  2. Communications TodayIndia's data centre capacity additions jump 59% in H1 2026 (Savills India) ↗
  3. Structure ResearchMumbai and Pune data centre report 2026 ↗
  4. Government of Maharashtra (gazette copy via Simpliance)Notification No. CEI-2025/CR-158/Energy-1 of 22 June 2026 under the Maharashtra Electricity Duty Act, 2016 ↗
  5. International Bar AssociationGreen data centres in India: policy meets practice ↗
  6. Bureau of Indian StandardsIS 1893 (Part 1):2002, criteria for earthquake resistant design, Annex E zone factors ↗
  7. NOAA National Centers for Environmental InformationGlobal hazards, July 2005 ↗
  8. AnarockData Centre: The Blueprint of the Digital Fortress in India (2026) ↗
  9. Tele.netGrowing gap: India’s subsea cable expansion outpaces its supporting infrastructure ↗
  10. EquinixEquinix launches purpose-built IBX data center in Mumbai ↗
  11. YottaData centers in India ↗
  12. AdaniConneXData centers ↗
  13. CoreWeaveCoreWeave enters India with AdaniConneX ↗
  14. Digital EdgeNavi Mumbai BOM2 topping out and BOM3 construction ↗
  15. W.MediaSTT GDC India breaks ground for data center campus in Palava ↗
  16. Deccan HeraldIndia set for five times surge in its data centre capacity by 2030 (Crisil Ratings) ↗
  17. Maharashtra Electricity Regulatory Commission (via MSEDCL)MERC Electricity Supply Code and Standards of Performance Regulations 2021 ↗
  18. Maharashtra Electricity Regulatory CommissionMERC MYT Order for MSEDCL, Case 217 of 2024 (28 March 2025) ↗
  19. Construction WorldMaharashtra allows data centres to generate green power ↗
  20. Cyril Amarchand MangaldasKey highlights of Maharashtra IT/ITES Policy 2023: data centers ↗
  21. Communications TodaySTT GDC India buys Navi Mumbai land for Rs 282 crore ↗
  22. DCDAWS acquires 38 acres near Mumbai for potential data center build ↗
  23. SEIAA MaharashtraEnvironmental clearance, Nxtra data centre, TTC Industrial Area, Mahape ↗
  24. Airports Authority of IndiaNOCAS frequently asked questions (height clearance under GSR 751(E)) ↗
  25. Business StandardNavi Mumbai airport begins commercial flight operations (25 December 2025) ↗