Andhra Pradesh data centre policy 4.0 (2024-29): incentives and mega projects

Andhra Pradesh data centre policy 4.0 (2024-29): SGST refund or a 10% capital subsidy; four projects cleared in 2026 with ₹2.83 lakh crore of proposed investment.

Andhra Pradesh’s Data Center Policy (4.0) 2024-29, notified through G.O.Ms.No.6 on 14 November 2024, offers data centres a choice between 100% net SGST reimbursement on capital goods and a 10% capital subsidy on plant and machinery. Both come with 100% stamp duty exemption on first sale and industrial power tariff. Projects above 50 MW, or above ₹5,000 crore of fixed capital investment in plant and equipment, can get tailor-made incentives case by case. In 2026 the state issued orders for four projects under the policy with ₹2,83,340 crore of proposed investment. The policy runs for five years from notification, or until a new policy is announced, whichever is later.

Before you start

  • Andhra Pradesh’s Data Center Policy 4.0 (G.O.Ms.No.6, 14 November 2024) offers 100% net SGST reimbursement on capital goods or a 10% capital subsidy on plant and machinery.
  • Under G.O.Ms.No.6, projects above 50 MW or ₹5,000 crore of fixed capital investment in plant and equipment can get tailor-made incentives case by case.
  • Andhra Pradesh issued government orders in 2026 for four data centre projects under the policy, with ₹2,83,340 crore of proposed investment.
  • The August 2026 order for ReNew’s 1,000 MW project in Anakapalli (G.O.Ms.No.55) caps its fiscal incentives at a combined ₹14,405 crore.
  • Crisil estimates Visakhapatnam data centre capacity could equal about 80% of the city’s current peak power demand by fiscal 2030.

Andhra Pradesh Data Center Policy 4.0: key facts

ItemDetail (checked 21 November 2026)
PolicyAndhra Pradesh Data Center Policy (4.0) 2024-29, G.O.Ms.No.6, ITE&C (Promotion Wing) Department
Notified14 November 2024
Validity5 years from notification, or until a new policy is announced, whichever is later
Target200 MW of additional capacity (G.O.); the annexed policy says a few hundred MW, up to 1 GW
Standard incentives100% net SGST reimbursement on capital goods or 10% capital subsidy on plant and machinery; 100% stamp duty exemption on first sale; industrial tariff
Mega projectsMore than 50 MW, or more than ₹5,000 crore of fixed capital investment in plant and equipment: tailor-made incentives case by case
2026 approvalsFour projects, ₹2,83,340 crore of proposed investment
Government of Andhra Pradesh (copy hosted by APIIC)Government of Andhra Pradesh, ITE&C Department (copy published by MediaNama)

Data centre projects Andhra Pradesh cleared in 2026

Andhra Pradesh issued government orders citing the Data Center Policy 4.0 for four projects in 2026. Three were issued in August 2026; Reliance’s land allotment was ordered in May 2026 and amended in July 2026.Government of Andhra Pradesh, ITE&C Department (copy published by MediaNama)MediaNama

ProjectLocationSize and investmentTerms in the government order
ReNew AP Green Data CenterMakavaripalem, Anakapalli district1,000 MW; ₹85,200 croreG.O.Ms.No.55, 21 August 2026: 10% capital subsidy on machinery and equipment (cap ₹3,700 crore), ₹1 per unit power discount for 15 years, fiscal caps totalling ₹14,405 crore
Data Centre Holdings India LLPJagnadhapuram, Visakhapatnam district486 MW; ₹58,743 croreG.O.Ms.No.56, 21 August 2026: 25% discount on APIIC land cost (cap ₹30 crore), ₹1 per unit power discount for 15 years
AM AI Factory (Vizag)Amanam, Visakhapatnam district512 MW; ₹31,387 croreG.O.Ms.No.59, 22 August 2026: 20 years of exemption from transmission and wheeling charges, electricity duty and cross-subsidy surcharge, each capped
Reliance IndustriesVizianagaram districtGiga-scale AI data centre; ₹1,08,010 croreLand at a 25% discounted rate (G.O.Ms.No.30, May 2026, amended by G.O.Ms.No.52, July 2026)
Government of Andhra Pradesh, ITE&C Department (copy published by MediaNama)

Power supply for data centres in Visakhapatnam

Crisil estimates that data centre capacity in Visakhapatnam could equal about 80% of the city’s current peak power demand by fiscal 2030. For any campus there, the transmission plan matters more than the incentive schedule.DD India

Google announced its first India AI hub in Visakhapatnam in October 2025, an investment of about USD 15 billion over 2026 to 2030, working with AdaniConneX and Airtel.Google

For a site in Andhra Pradesh, Invariant checks how it gets power and the evidence behind that path (the distribution or transmission connection, the open access route, the nearest substations), screens seismic zone, flood history, groundwater status and airport height limits, and maps the central and state approvals the project needs, with the authority behind each one.

More on data centres in India

Questions that come up.

What is the Andhra Pradesh data centre policy 4.0?

It is the state’s Data Center Policy (4.0) 2024-29, notified through G.O.Ms.No.6 on 14 November 2024. It is valid for five years from notification or until a new policy is announced, whichever is later.Government of Andhra Pradesh (copy hosted by APIIC)

What incentives does the Andhra Pradesh data centre policy give?

Andhra Pradesh offers a choice between 100% net SGST reimbursement on capital goods and a 10% capital subsidy on plant and machinery. Both come with 100% stamp duty exemption on first sale and industrial power tariff. Incentives are extended under operational guidelines notified separately.Government of Andhra Pradesh (copy hosted by APIIC)

What counts as a mega data centre project in Andhra Pradesh?

A project of more than 50 MW, or more than ₹5,000 crore of fixed capital investment in plant and equipment. It can get tailor-made incentives case by case.Government of Andhra Pradesh (copy hosted by APIIC)

Which data center projects did Andhra Pradesh approve in 2026?

Andhra Pradesh issued orders for four projects with ₹2,83,340 crore of proposed investment in total. They are ReNew (1,000 MW, Anakapalli), Data Centre Holdings India LLP (486 MW, Visakhapatnam), AM AI Factory (512 MW, Visakhapatnam) and a Reliance giga-scale AI data centre in Vizianagaram.Government of Andhra Pradesh, ITE&C Department (copy published by MediaNama)

How big is Google’s investment in Visakhapatnam?

Google says it will invest about USD 15 billion over 2026 to 2030 in its first India AI hub, in Visakhapatnam.Google

Is there enough power for data centres in Visakhapatnam?

Power is the main open question for Visakhapatnam. Crisil estimates data centre capacity there could equal about 80% of the city’s current peak demand by fiscal 2030.DD India

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. Government of Andhra Pradesh (copy hosted by APIIC)Andhra Pradesh Data Center Policy (4.0) 2024-29, G.O.Ms.No.6, ITE&C (Promotion Wing) Department, 14 November 2024 ↗
  2. Government of Andhra Pradesh, ITE&C Department (copy published by MediaNama)Andhra Pradesh ITE&C G.O.Ms.No.52, 55, 56 and 59 of 2026 on data centre projects (combined copy) ↗
  3. MediaNamaAndhra Pradesh clears AI data centre projects ↗
  4. GoogleOur first AI hub in India, powered by a $15 billion investment ↗
  5. DD IndiaIndia's data centre capacity set for 5x surge by 2030 (Crisil Ratings) ↗