Data centres in Gujarat: Jamnagar, GIFT City, Ahmedabad and Dholera (2026)

Data centres in Gujarat: Reliance’s Jamnagar AI campus, Yotta at GIFT City and a planned 250 MW Dholera campus, under a 2026-29 policy for 150 MW or larger projects.

Gujarat’s data centre activity centres on Jamnagar, where Mukesh Ambani said in February 2026 that Reliance had begun building multi-gigawatt data centres, with more than 120 MW expected online in the second half of 2026. Meta agreed in June 2026 to lease capacity at a 168 MW Reliance facility there. GIFT City hosts Yotta’s 1 MW G1 facility, and L&T Vyoma signed an MoU for a 250 MW green data centre at Dholera. The Viksit Gujarat Data Centre Policy 2026-29, launched on 9 July 2026, supports only projects of 150 MW or more, with incentives available until 7.5 GW of capacity is reached statewide.

Before you start

  • Jamnagar: Reliance AI campus; Meta leasing capacity at a 168 MW facility (June 2026); Google and Reliance dedicated AI cloud region announced (August 2025). Invest India and Cushman & Wakefield map Jamnagar at 1 GW+ early stage; Anarock lists a 3 GW campus.
  • Gujarat’s 2026-29 policy requires at least 150 MW of approved IT load and 51% green power for core operations, and, according to Cyril Amarchand Mangaldas, treats data centre operations as an essential service under the Gujarat ESMA 1972.
  • GIFT City: Yotta’s G1 facility lists 350 racks and 1 MW of IT load. The Union Budget 2023-24 announced that the government would facilitate data embassies in GIFT IFSC.
  • Dholera: L&T Vyoma signed an MoU with Gujarat for a 250 MW green data centre, Rs 25,000 crore, with operations expected by 2028.

Gujarat data centres: key facts (2026)

ItemFigure and period
JamnagarReliance multi-gigawatt AI data centres under construction; more than 120 MW expected online in H2 2026 (Reliance, February 2026); Meta leasing capacity at a 168 MW facility (June 2026)
Jamnagar scale estimates1 GW+ early stage (Invest India and Cushman & Wakefield map); 3 GW campus (Anarock)
GIFT CityYotta G1: 1 MW IT load, 350 racks
DholeraL&T Vyoma 250 MW green data centre MoU, Rs 25,000 crore (February 2026)
State policyViksit Gujarat Data Centre Policy 2026-29, launched 9 July 2026; incentives until 7.5 GW statewide
CablesTwo cable landing stations planned in Gujarat (announced at the policy launch, July 2026)
Physical risk noteAhmedabad Seismic Zone III; Bhuj (Kutch) Zone V
TechCrunchTechCrunchInvest India and Cushman & WakefieldAnarockYottaAll India Radio NewsDD IndiaCyril Amarchand MangaldasBureau of Indian Standards

Jamnagar: Reliance’s AI data centre campus

Reliance said on 19 February 2026 that construction of multi-gigawatt data centres at Jamnagar had begun, with more than 120 MW expected online in the second half of 2026, supported by 10 GW of surplus solar power in Gujarat and Andhra Pradesh. The announcement came with a Rs 10 trillion (about US$110 billion) plan to build AI computing infrastructure over seven years. Reliance and Google announced a dedicated AI cloud region, starting with a data centre in Jamnagar, in August 2025.TechCrunchTechCrunch

Meta announced its first Indian AI data centre partnership with Reliance on 10 June 2026: Meta is leasing capacity at a 168 MW facility at Jamnagar that Reliance said will be ready within two years, powered by renewable energy and cooled with desalinated seawater.TechCrunch

GIFT City, Ahmedabad and Dholera

GIFT City, India’s first international financial services centre, at Gandhinagar, hosts Yotta’s G1 facility with 1 MW of IT load. In the Union Budget 2023-24 the Finance Minister said the government would facilitate data embassies in GIFT IFSC for countries looking for digital continuity solutions.YottaInc42

At the India AI Impact Summit in February 2026, Gujarat signed an MoU with L&T Vyoma for a 250 MW green data centre at the Dholera Special Investment Region, with Rs 25,000 crore of investment and operations expected by 2028. The state policy document highlights Dholera and GIFT City among Gujarat’s industrial hubs.All India Radio NewsDD India

Gujarat data centre policy 2026-29: eligibility and incentives

  • Projects eligible under the Viksit Gujarat Data Centre Policy 2026-29 need at least 150 MW of approved installed IT load, and at least 51% of electricity for core operations must come from green and renewable energy.
  • Power tariff subsidy of Rs 1 per unit for 20 years; 100% electricity duty reimbursement for 20 years; 100% stamp duty and registration fee exemption on lease or purchase of land.
  • Interest subsidy up to 4% a year for 10 years (capped at Rs 25 crore a year); capital subsidy of 2.5% of eligible fixed capital investment for projects solely in Dholera SIR; total incentives capped at 75% of eligible fixed capital investment.
  • Open access permitted and dual power supply through two independent feeders; data centre operations treated as an essential service under the Gujarat Essential Services Maintenance Act, 1972, according to Cyril Amarchand Mangaldas.
  • Operative for three years from notification (extendable), with incentives available only until 7.5 GW of installed capacity is reached statewide.
Cyril Amarchand Mangaldas

Cyril Amarchand Mangaldas describes the policy as designed for hyperscale and large data centre developments, in contrast to the previous framework for smaller projects.Cyril Amarchand Mangaldas

Site risks for data centres in Gujarat

  • Seismic: Ahmedabad is Zone III (zone factor 0.16) in the IS 1893 (Part 1):2002 town list, while Bhuj in Kutch is Zone V (zone factor 0.36). Check the zone for the specific site.
  • Water: Reliance’s 168 MW Jamnagar facility for Meta will be cooled with desalinated seawater, and the state policy offers a capital subsidy for captive desalination plants.
Bureau of Indian StandardsTechCrunchCyril Amarchand Mangaldas

Invariant checks the evidence behind a site’s power (the DISCOM or transmission connection, the open access route, the nearest substations and what else is queued on them), screens seismic zone, flood history, groundwater status and airport height limits, and lists the central and state approvals the project needs with the authority behind each one. In Gujarat, we check the 150 MW policy floor and the water source alongside the power route.

More on data centres in India

Questions that come up.

Where is the largest data centre project in Gujarat?

Jamnagar is the largest of the Gujarat locations that Invest India and Cushman & Wakefield map, at 1 GW+ early stage. Meta is leasing capacity at a 168 MW Reliance facility there, and Reliance said more than 120 MW was expected online in H2 2026.Invest India and Cushman & WakefieldTechCrunchTechCrunch

Is Meta building a data centre in Gujarat?

Meta announced on 10 June 2026 that it is leasing capacity at a 168 MW Reliance facility at Jamnagar, its first Indian AI data centre partnership. Reliance said the facility will be ready within two years, powered by renewable energy and cooled with desalinated seawater.TechCrunch

Is there a data center in GIFT City?

Yes. Yotta’s G1 facility in GIFT City lists 1 MW of IT load and 350 racks.Yotta

What is the Gujarat data centre policy 2026-29?

The Viksit Gujarat Data Centre Policy 2026-29, launched 9 July 2026, supports projects of at least 150 MW using at least 51% green power for core operations. It offers a power tariff subsidy of Rs 1 per unit for 20 years, electricity duty reimbursement, stamp duty exemption and, according to Cyril Amarchand Mangaldas, essential-service status. Incentives run until 7.5 GW is reached statewide.DD IndiaCyril Amarchand Mangaldas

What data centre is planned at Dholera?

L&T Vyoma signed an MoU with Gujarat for a 250 MW green data centre at Dholera, worth about Rs 25,000 crore. Operations are expected to start by 2028.All India Radio News

Sources and references.

Primary sources checked for this guide on . The location, equipment, and operating plan determine which requirements apply to a project.

  1. TechCrunchReliance unveils $110B AI investment plan ↗
  2. TechCrunchMeta signs first AI data center deal in India with Reliance ↗
  3. Invest India and Cushman & WakefieldIndia's Data Centre Growth Story (October 2026) ↗
  4. AnarockData Centre: The Blueprint of the Digital Fortress in India (2026) ↗
  5. YottaData centers in India ↗
  6. All India Radio NewsGujarat signs agreement with Larsen & Toubro Vyoma to build AI data center in Dholera ↗
  7. DD IndiaGujarat launches Data Centre Policy 2026-29 ↗
  8. Bureau of Indian StandardsIS 1893 (Part 1):2002, criteria for earthquake resistant design, Annex E zone factors ↗
  9. TechCrunchBillionaire Ambani taps Google, Meta to build India’s AI backbone ↗
  10. Inc42Union Budget 2023-24: govt to facilitate data embassies in GIFT City ↗
  11. Cyril Amarchand MangaldasGujarat Data Center Policy 2026-2029: a push for large-scale data center infrastructure ↗